8867-8869 N ONEIDA AVE 91352
Certificate Information: 8867-8869 N ONEIDA AVE 91352
- Application / Permit
- 24016-20000-24331
- Plan Check / Job No.
- B24VN11410
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN: CONVERSION OF ATTACHED GARAGE INTO ADU PER ORDINANCE AND LAMC 12.22 A33(c)&(e)
- Permit Issued
- Issued on 9/5/2024
- Issuing Office
- Current Status
- CofO Issued on 4/10/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/30/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/2/2024 | ZAW HAN |
| Corrections Issued | 8/2/2024 | ZAW HAN |
| Applicant returned to address corrections | 8/12/2024 | ZAW HAN |
| Plan Check Approved | 8/19/2024 | ADAM HEGAZI |
| Issued | 9/5/2024 | APPLICANT |
| CofO in Progress | 4/1/2025 | MATTHEW NELSON |
| Permit Finaled | 4/10/2025 | RUBEN SALAS |
| CofO Issued | 4/10/2025 | RUBEN SALAS |
| Permit Finaled | 4/10/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 8/5/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 8/5/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 8/5/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 8/5/2024 | BIAINA HARITUNIAN |
| Clean Up Green Up | Cleared | 8/9/2024 | ALEX VELA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Nguyen,, Quynh Anh; Lic. No.: NA58592 | , |
Inspector Information
| WILLIAM WREN, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/21/2024 | Conditional Approval | DAVID MATSON |
| BUILDING-Rough-Frame | 10/22/2024 | Not Ready for Inspection | MATTHEW NELSON |
| Gas Test | 10/22/2024 | Not Ready for Inspection | MATTHEW NELSON |
| Green Building Rough | 10/22/2024 | Not Ready for Inspection | MATTHEW NELSON |
| MERV13>=Rough | 10/22/2024 | Not Ready for Inspection | MATTHEW NELSON |
| PLUMBING-Rough | 10/22/2024 | Partial Approval | MATTHEW NELSON |
| Wood Frame | 10/22/2024 | Not Ready for Inspection | MATTHEW NELSON |
| ELECTRICAL-Rough | 11/15/2024 | Approved | MATTHEW NELSON |
| HVAC-Rough | 11/15/2024 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 11/15/2024 | Approved | MATTHEW NELSON |
| Wood Frame | 11/15/2024 | Not Ready for Inspection | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/10/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Insulation | 12/10/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 12/18/2024 | Partial Approval | MATTHEW NELSON |
| Green Building Rough | 12/18/2024 | Approved | MATTHEW NELSON |
| MERV13>=Rough | 12/18/2024 | Approved | MATTHEW NELSON |
| Insulation | 12/20/2024 | Partial Approval | MATTHEW NELSON |
| BUILDING-Rough-Frame | 12/31/2024 | Approved | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/31/2024 | Approved | MATTHEW NELSON |
| Drywall Nailing | 1/17/2025 | Approved | MATTHEW NELSON |
| Final | 3/25/2025 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 3/25/2025 | Approved | MATTHEW NELSON |
| MERV13>=Final | 3/25/2025 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 3/25/2025 | SGSOV Approved | MATTHEW NELSON |
| Smoke Detectors | 3/25/2025 | Approved | MATTHEW NELSON |
| Final | 3/28/2025 | OK to Issue CofO | MATTHEW NELSON |