10345 N SEPULVEDA BLVD 91345

Certificate Information: 10345 N SEPULVEDA BLVD 91345

Application / Permit
24016-20000-24160
Plan Check / Job No.
B24VN11246
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(16) Retail
Work Description
<ePLAN> Remove portion of building now as 10345 Sepulveda and add CMU wall to 10343 Sepulveda
Permit Issued
Issued on 1/17/2025
Issuing Office
Current Status
Permit Finaled on 5/20/2025

Permit Application Status History

Submitted 7/30/2024 APPLICANT
Assigned to Plan Check Engineer 8/1/2024 MARVEL DELACRUZ
Assigned to Zoning Architect 8/1/2024 FRANCIS AHN
Corrections Issued 8/4/2024 MARVEL DELACRUZ
Quality Review Completed 8/8/2024 OMID HEDAYAT
Applicant returned to address corrections 9/6/2024 MARVEL DELACRUZ
Applicant returned to address corrections 9/10/2024 MARVEL DELACRUZ
Applicant returned to address corrections 9/17/2024 MARVEL DELACRUZ
Applicant returned to address corrections 10/3/2024 MARVEL DELACRUZ
Plan Check Approved 11/7/2024 MARVEL DELACRUZ
Issued 1/17/2025 APPLICANT
Permit Finaled 5/20/2025 ANDREW DORSO

Permit Application Clearance Information

Green Code Cleared 9/6/2024 MICHAEL AYERS
DAS Clearance Cleared 9/20/2024 Mina Habili
Miscellaneous Cleared 10/7/2024 NATHAN ROMINE
Miscellaneous Cleared 10/7/2024 NATHAN ROMINE
ZA Case Cleared 10/7/2024 NATHAN ROMINE
ZA Case Cleared 10/7/2024 NATHAN ROMINE
ZA Case Cleared 10/7/2024 NATHAN ROMINE
Eng Process Fee Ord 176,300 Cleared 10/22/2024 EDGAR ALCARAZ
Sewer availability Cleared 10/22/2024 EDGAR ALCARAZ
Zoning Plan Check Cleared 10/29/2024 Mina Habili

Contact Information

Architect Malak,, Hany; Lic. No.: NA27490       ,
Contractor Bergman Build,Llc; Lic. No.: 982577-B       ,
Engineer Chan,, Dominic Kam-Tim; Lic. No.: NA4381       ,

Inspector Information

ANDREW DORSO, (818) 374-7520 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/18/2025 Partial Inspection ANDREW DORSO
Deputy Grading 3/5/2025 Conditional Approval ANDREW DORSO
Deputy Reinf. Concrete 3/5/2025 Conditional Approval ANDREW DORSO
Footing/Foundation/Slab 3/5/2025 Not Ready for Inspection ANDREW DORSO
Reinforced Concrete Frame 3/5/2025 Not Ready for Inspection ANDREW DORSO
Reinforced Masonry Frame 3/5/2025 Not Ready for Inspection ANDREW DORSO
Footing/Foundation/Slab 3/6/2025 Partial Inspection ANDREW DORSO
Deputy Steel/Welding 3/7/2025 Conditional Approval ANDREW DORSO
Deputy Steel/Welding 3/12/2025 Conditional Approval ANDREW DORSO
Green Building Rough 3/12/2025 Approved ANDREW DORSO
Wood Frame 3/12/2025 Partial Inspection ANDREW DORSO
Excavation/Setback/Form/Re-Bar 3/18/2025 Partial Inspection ANDREW DORSO
Wood Frame 3/18/2025 Partial Inspection ANDREW DORSO
Deputy Steel/Welding 3/19/2025 Conditional Approval ANDREW DORSO
Excavation/Setback/Form/Re-Bar 3/20/2025 Partial Inspection ANDREW DORSO
Masonry Wall/Backfill 3/20/2025 Partial Inspection ANDREW DORSO
Excavation/Setback/Form/Re-Bar 3/21/2025 Partial Inspection ANDREW DORSO
Masonry Wall/Backfill 3/21/2025 Partial Inspection ANDREW DORSO
Excavation/Setback/Form/Re-Bar 3/25/2025 Partial Inspection ANDREW DORSO
Masonry Wall/Backfill 3/25/2025 Partial Inspection ANDREW DORSO
Wood Frame 4/3/2025 Partial Approval GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 4/9/2025 Partial Approval GREGORY POMISH
Interior/Exterior Lathing 4/9/2025 Not Ready for Inspection GREGORY POMISH
Interior/Exterior Lathing 4/11/2025 Approved GREGORY POMISH
Wood Frame 4/11/2025 Approved GREGORY POMISH
Deputy Drilled-In Anchors 5/1/2025 Conditional Approval ANDREW DORSO
Final 5/2/2025 Partial Approval ANDREW DORSO
Green Building Final 5/2/2025 Approved ANDREW DORSO
SGSOV-Seismic Gas S/O Valve 5/2/2025 SGSOV Approved ANDREW DORSO
Smoke Detectors 5/2/2025 Approved ANDREW DORSO
Final 5/12/2025 Partial Inspection ANDREW DORSO
Final 5/20/2025 Permit Finaled ANDREW DORSO