10345 N SEPULVEDA BLVD 91345
Certificate Information: 10345 N SEPULVEDA BLVD 91345
- Application / Permit
- 24016-20000-24160
- Plan Check / Job No.
- B24VN11246
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- <ePLAN> Remove portion of building now as 10345 Sepulveda and add CMU wall to 10343 Sepulveda
- Permit Issued
- Issued on 1/17/2025
- Issuing Office
- Current Status
- Permit Finaled on 5/20/2025
Permit Application Status History
| Submitted | 7/30/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/1/2024 | MARVEL DELACRUZ |
| Assigned to Zoning Architect | 8/1/2024 | FRANCIS AHN |
| Corrections Issued | 8/4/2024 | MARVEL DELACRUZ |
| Quality Review Completed | 8/8/2024 | OMID HEDAYAT |
| Applicant returned to address corrections | 9/6/2024 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 9/10/2024 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 9/17/2024 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 10/3/2024 | MARVEL DELACRUZ |
| Plan Check Approved | 11/7/2024 | MARVEL DELACRUZ |
| Issued | 1/17/2025 | APPLICANT |
| Permit Finaled | 5/20/2025 | ANDREW DORSO |
Permit Application Clearance Information
| Green Code | Cleared | 9/6/2024 | MICHAEL AYERS |
| DAS Clearance | Cleared | 9/20/2024 | Mina Habili |
| Miscellaneous | Cleared | 10/7/2024 | NATHAN ROMINE |
| Miscellaneous | Cleared | 10/7/2024 | NATHAN ROMINE |
| ZA Case | Cleared | 10/7/2024 | NATHAN ROMINE |
| ZA Case | Cleared | 10/7/2024 | NATHAN ROMINE |
| ZA Case | Cleared | 10/7/2024 | NATHAN ROMINE |
| Eng Process Fee Ord 176,300 | Cleared | 10/22/2024 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 10/22/2024 | EDGAR ALCARAZ |
| Zoning Plan Check | Cleared | 10/29/2024 | Mina Habili |
Contact Information
| Architect | Malak,, Hany; Lic. No.: NA27490 | , |
| Contractor | Bergman Build,Llc; Lic. No.: 982577-B | , |
| Engineer | Chan,, Dominic Kam-Tim; Lic. No.: NA4381 | , |
Inspector Information
| ANDREW DORSO, (818) 374-7520 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/18/2025 | Partial Inspection | ANDREW DORSO |
| Deputy Grading | 3/5/2025 | Conditional Approval | ANDREW DORSO |
| Deputy Reinf. Concrete | 3/5/2025 | Conditional Approval | ANDREW DORSO |
| Footing/Foundation/Slab | 3/5/2025 | Not Ready for Inspection | ANDREW DORSO |
| Reinforced Concrete Frame | 3/5/2025 | Not Ready for Inspection | ANDREW DORSO |
| Reinforced Masonry Frame | 3/5/2025 | Not Ready for Inspection | ANDREW DORSO |
| Footing/Foundation/Slab | 3/6/2025 | Partial Inspection | ANDREW DORSO |
| Deputy Steel/Welding | 3/7/2025 | Conditional Approval | ANDREW DORSO |
| Deputy Steel/Welding | 3/12/2025 | Conditional Approval | ANDREW DORSO |
| Green Building Rough | 3/12/2025 | Approved | ANDREW DORSO |
| Wood Frame | 3/12/2025 | Partial Inspection | ANDREW DORSO |
| Excavation/Setback/Form/Re-Bar | 3/18/2025 | Partial Inspection | ANDREW DORSO |
| Wood Frame | 3/18/2025 | Partial Inspection | ANDREW DORSO |
| Deputy Steel/Welding | 3/19/2025 | Conditional Approval | ANDREW DORSO |
| Excavation/Setback/Form/Re-Bar | 3/20/2025 | Partial Inspection | ANDREW DORSO |
| Masonry Wall/Backfill | 3/20/2025 | Partial Inspection | ANDREW DORSO |
| Excavation/Setback/Form/Re-Bar | 3/21/2025 | Partial Inspection | ANDREW DORSO |
| Masonry Wall/Backfill | 3/21/2025 | Partial Inspection | ANDREW DORSO |
| Excavation/Setback/Form/Re-Bar | 3/25/2025 | Partial Inspection | ANDREW DORSO |
| Masonry Wall/Backfill | 3/25/2025 | Partial Inspection | ANDREW DORSO |
| Wood Frame | 4/3/2025 | Partial Approval | GREGORY POMISH |
| Floor/Roof Diaphrgm/Shear Wall | 4/9/2025 | Partial Approval | GREGORY POMISH |
| Interior/Exterior Lathing | 4/9/2025 | Not Ready for Inspection | GREGORY POMISH |
| Interior/Exterior Lathing | 4/11/2025 | Approved | GREGORY POMISH |
| Wood Frame | 4/11/2025 | Approved | GREGORY POMISH |
| Deputy Drilled-In Anchors | 5/1/2025 | Conditional Approval | ANDREW DORSO |
| Final | 5/2/2025 | Partial Approval | ANDREW DORSO |
| Green Building Final | 5/2/2025 | Approved | ANDREW DORSO |
| SGSOV-Seismic Gas S/O Valve | 5/2/2025 | SGSOV Approved | ANDREW DORSO |
| Smoke Detectors | 5/2/2025 | Approved | ANDREW DORSO |
| Final | 5/12/2025 | Partial Inspection | ANDREW DORSO |
| Final | 5/20/2025 | Permit Finaled | ANDREW DORSO |