1042 W DOWNEY WAY Basement 90089
Certificate Information: 1042 W DOWNEY WAY Basement 90089
- Application / Permit
- 24016-20000-24077
- Plan Check / Job No.
- B24VN11180
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (18) School Building
- Work Description
- eplan: tenant improvement Miscellaneous alterations in basement rooms B1, B7, B18 including minor framing, patch and repair of existing finishes, new casework, and minor utility alterations.
- Permit Issued
- Issued on 11/12/2024
- Issuing Office
- Current Status
- Issued on 11/12/2024
Permit Application Status History
| Submitted | 7/30/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/2/2024 | TSE MING HUANG |
| Corrections Issued | 8/3/2024 | TSE MING HUANG |
| Plan Check Approved | 8/25/2024 | TSE MING HUANG |
| Issued | 11/12/2024 | APPLICANT |
Permit Application Clearance Information
| Historic Resource Verification | Cleared | 8/6/2024 | LAMBERT GIESSINGER |
| Specific Plan | Cleared | 8/7/2024 | MANERI ROMAN |
| Redevelopment Project Area | Cleared | 8/8/2024 | ELIZABETH GALLARDO |
Contact Information
| Architect | Dontje,, Jason Alan; Lic. No.: C32176 | 2240 RALEIGH AVENUE COSTA MESA, CA 92627 |
| Architect | Dontje,, Jason Alan; Lic. No.: NA32176 | , |
| Contractor | Lcs Constructors Inc; Lic. No.: 640058-B | , |
| Contractor | Lcs Constructors, Inc.; Lic. No.: 640058-B | , |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Structural Steel Frame | 12/5/2024 | Not Ready for Inspection | ALFREDO LOPEZ |
| Drywall Nailing | 12/12/2024 | Not Ready for Inspection | ALFREDO LOPEZ |
| Footing/Foundation/Slab | 12/12/2024 | Approved | ALFREDO LOPEZ |
| Structural Steel Frame | 12/12/2024 | Approved | ALFREDO LOPEZ |
| Drywall Nailing | 2/3/2025 | Partial Approval | ALFREDO LOPEZ |
| Wood Frame | 3/4/2025 | Not Ready for Inspection | ALFREDO LOPEZ |
| Wood Frame | 3/26/2025 | Not Ready for Inspection | ALFREDO LOPEZ |
| Final | 9/2/2025 | Not Ready for Inspection | ALFREDO LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 9/2/2025 | SGSOV Not Ready | ALFREDO LOPEZ |
| Smoke Detectors | 9/2/2025 | Not Ready for Inspection | ALFREDO LOPEZ |
| Final | 9/8/2025 | Conditional Approval | ALFREDO LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 9/8/2025 | SGSOV Not Required | ALFREDO LOPEZ |
| Smoke Detectors | 9/8/2025 | Approved | ALFREDO LOPEZ |