11533-11535 N CURRY AVE 91344

Certificate Information: 11533-11535 N CURRY AVE 91344

Application / Permit
24016-20000-23981
Plan Check / Job No.
B24VN11086
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN: Existing Attached Garage (400 SF) and Breezeway ( 8'-11" x 17'-2") Convert to ADU. GCS 65852.2 (e)(1)(A)
Permit Issued
Issued on 10/1/2024
Issuing Office
Current Status
CofO Issued on 5/2/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/29/2024 APPLICANT
Assigned to Plan Check Engineer 8/1/2024 TSE MING HUANG
Corrections Issued 8/2/2024 TSE MING HUANG
Applicant returned to address corrections 9/13/2024 TSE MING HUANG
Plan Check Approved 9/27/2024 TSE MING HUANG
Issued 10/1/2024 APPLICANT
CofO in Progress 2/25/2025 JEFFREY PARD
No Progress 4/2/2025 HENRY KIM
CofO in Progress 4/2/2025 HENRY KIM
Permit Finaled 5/2/2025 JOHN JANSON
CofO Issued 5/2/2025 JOHN JANSON
Permit Finaled 5/2/2025 JOHN JANSON

Permit Application Clearance Information

Grading Pre-Inspection Cleared 8/16/2024 CHARLES POWELL
Address approval Cleared 8/20/2024 BIAINA HARITUNIAN
Sewer availability Cleared 8/20/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 8/21/2024 BIAINA HARITUNIAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/2/2024 Approved JEFFREY PARD
Footing/Foundation/Slab 10/4/2024 Corrections Issued STEVEN BACK
Deputy Drilled-In Anchors 10/7/2024 Approved JEFFREY PARD
Excavation/Setback/Form/Re-Bar 10/10/2024 Approved DAVID SCANTLIN
Final 10/10/2024 Corrections Issued DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 10/17/2024 Approved STEVEN BACK
PLUMBING-Rough 12/5/2024 Corrections Issued STEVEN BACK
PLUMBING-Rough 12/9/2024 Partial Approval STEVEN BACK
ELECTRICAL-Rough 12/16/2024 Approved STEVEN BACK
HVAC-Rough 12/16/2024 Not Ready for Inspection STEVEN BACK
HVAC-Rough 12/18/2024 Not Ready for Inspection STEVEN BACK
BUILDING-Rough-Frame 12/23/2024 Corrections Issued STEVEN BACK
HVAC-Rough 12/23/2024 Approved STEVEN BACK
BUILDING-Rough-Frame 12/27/2024 Approved STEVEN BACK
MERV13>=Rough 12/27/2024 Approved STEVEN BACK
Drywall Nailing 1/8/2025 Approved STEVEN BACK
Insulation 1/8/2025 Approved STEVEN BACK
Interior/Exterior Lathing 1/8/2025 Approved STEVEN BACK
Shower Pan 1/8/2025 Approved STEVEN BACK
Final 2/10/2025 Corrections Issued JEFFREY PARD
MERV13>=Final 2/10/2025 Approved JEFFREY PARD
SGSOV-Seismic Gas S/O Valve 2/10/2025 SGSOV Not Ready JEFFREY PARD
Smoke Detectors 2/10/2025 Approved JEFFREY PARD
Final 2/13/2025 OK to Issue CofO JEFFREY PARD
SGSOV-Seismic Gas S/O Valve 2/13/2025 SGSOV Approved JEFFREY PARD
Pre-Inspection 4/8/2025 Corrections Issued JEFFREY PARD