374 1/4 N AVENUE 52 90042

Certificate Information: 374 1/4 N AVENUE 52 90042

Application / Permit
24016-20000-23938
Plan Check / Job No.
B24VN11048
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT DETACHED GARAGE TO (N) 435 SF ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(D) and applicable part of LAMC 12.22 A.33 (c)-(d), (g), AND EXTERIOR ALTERATION TO REMOVED ATTACHED CARPORT.
Permit Issued
Issued on 1/6/2025
Issuing Office
Valley
Current Status
Issued on 1/6/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/26/2024 APPLICANT
Assigned to Plan Check Engineer 8/1/2024 ANGELICA DAVE
Corrections Issued 8/1/2024 ANGELICA DAVE
Building Plans Picked Up 8/2/2024 APPLICANT
Plan Check Approved 1/3/2025 LUISANGEL VALENZUELA
Issued 1/6/2025 APPLICANT

Permit Application Clearance Information

Sewer availability Cleared 9/5/2024 CHRISTINA BRACO
Grading Pre-Inspection Cleared 9/20/2024 MICHAEL TEMPLE
Eng Process Fee Ord 176,300 Cleared 10/1/2024 CHRISTINA BRACO
HPOZ Cleared 11/14/2024 NATHALY DE LA PAZ
Address approval Cleared 1/2/2025 CHRISTINA BRACO

Contact Information

Contractor Sarahang Construction Inc; Lic. No.: 897724-B 39312 DUNBAR      PALMDALE, CA 93551

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/20/2025 Partial Approval THOMAS LOGRASSO
Footing/Foundation/Slab 2/27/2025 Corrections Issued NICHOLAS LOPEZ
Deputy Drilled-In Anchors 4/1/2025 Conditional Approval NICHOLAS LOPEZ
Footing/Foundation/Slab 4/3/2025 Approved NICHOLAS LOPEZ
ELECTRICAL-Rough 4/16/2025 Approved NICHOLAS LOPEZ
Floor/Roof Diaphrgm/Shear Wall 4/16/2025 Approved NICHOLAS LOPEZ
HVAC-Rough 4/16/2025 Approved NICHOLAS LOPEZ
Underground Mechanical 4/16/2025 Approved NICHOLAS LOPEZ
Wood Frame 4/16/2025 Not Ready for Inspection NICHOLAS LOPEZ
BUILDING-Rough-Frame 4/22/2025 Conditional Approval NICHOLAS LOPEZ
Green Building Rough 4/22/2025 Approved NICHOLAS LOPEZ
Interior/Exterior Lathing 4/22/2025 Partial Approval NICHOLAS LOPEZ
PLUMBING-Rough 4/22/2025 Approved NICHOLAS LOPEZ
Drywall Nailing 5/1/2025 Not Ready for Inspection REGINA MENDEZ
Insulation 5/1/2025 Approved REGINA MENDEZ
Interior/Exterior Lathing 5/1/2025 Approved REGINA MENDEZ
Drywall Nailing 5/6/2025 Approved REGINA MENDEZ
BUILDING-Rough-Frame 6/3/2025 Approved NICHOLAS LOPEZ
Final 6/3/2025 Corrections Issued NICHOLAS LOPEZ
Green Building Final 6/3/2025 Not Ready for Inspection NICHOLAS LOPEZ
SGSOV-Seismic Gas S/O Valve 6/3/2025 SGSOV Not Ready NICHOLAS LOPEZ
Smoke Detectors 6/3/2025 Approved NICHOLAS LOPEZ
Final 6/26/2025 Not Ready for Inspection LILIANA PORTILLO
Green Building Final 6/26/2025 Not Ready for Inspection LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 6/26/2025 SGSOV Approved LILIANA PORTILLO