6141 1/2 W OLYMPIC BLVD 90048
Certificate Information: 6141 1/2 W OLYMPIC BLVD 90048
- Application / Permit
- 24016-20000-23886
- Plan Check / Job No.
- B24VN10995
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT GARAGE AND STORAGE WITH UNPERMITTED PORTION TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(b)(1)3
- Permit Issued
- Issued on 2/4/2025
- Issuing Office
- Current Status
- CofO Issued on 2/23/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/26/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/1/2024 | JESSE ARELLANO |
| Corrections Issued | 8/1/2024 | JESSE ARELLANO |
| Building Plans Picked Up | 8/8/2024 | APPLICANT |
| Applicant returned to address corrections | 2/3/2025 | ARAMIK SHAHMIRZAIAN |
| Plan Check Approved | 2/4/2025 | NAREG ATARIAN |
| Issued | 2/4/2025 | APPLICANT |
| Permit Finaled | 2/23/2026 | DEROLD HAUFF |
| CofO Issued | 2/23/2026 | DEROLD HAUFF |
| Permit Finaled | 2/23/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/13/2024 | WALLIE JONG |
| Sewer availability | Cleared | 8/13/2024 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 8/14/2024 | WALLIE JONG |
| City Hist. Cultural Monument | Cleared | 11/18/2024 | RAFAEL FONTES |
| Historic Resource Verification | Cleared | 11/18/2024 | RAFAEL FONTES |
| Historic monument | Cleared | 11/18/2024 | RAFAEL FONTES |
| Redevelopment Project Area | Cleared | 11/18/2024 | RAFAEL FONTES |
| HPOZ | Cleared | 1/31/2025 | DEBORAH MCGILL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 60 VIA CARATAMA SAN CLEMENTE, CA 92673 |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/28/2025 | Approved | JOSE MACIAS |
| PLUMBING-Rough | 4/14/2025 | Partial Approval | RONNIE MINDANAO |
| Sewer | 4/14/2025 | Approved | RONNIE MINDANAO |
| Underground Mechanical | 4/14/2025 | Approved | RONNIE MINDANAO |
| Footing/Foundation/Slab | 4/18/2025 | Corrections Issued | RONNIE MINDANAO |
| Footing/Foundation/Slab | 4/21/2025 | No Access for Inspection | RONNIE MINDANAO |
| Footing/Foundation/Slab | 4/29/2025 | Corrections Issued | RONNIE MINDANAO |
| Deputy Drilled-In Anchors | 5/6/2025 | Conditional Approval | RONNIE MINDANAO |
| Footing/Foundation/Slab | 5/6/2025 | Approved | RONNIE MINDANAO |
| Pre-Inspection | 5/19/2025 | Partial Inspection | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 6/4/2025 | SGSOV Not Ready | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 6/11/2025 | Corrections Issued | WILLIAM SIERRA |
| ELECTRICAL-Rough | 6/11/2025 | Approved | WILLIAM SIERRA |
| Green Building Rough | 6/11/2025 | Corrections Issued | WILLIAM SIERRA |
| HVAC-Rough | 6/11/2025 | Corrections Issued | WILLIAM SIERRA |
| PLUMBING-Rough | 6/11/2025 | Approved | WILLIAM SIERRA |
| HVAC-Rough | 6/16/2025 | Corrections Issued | JOSE MACIAS |
| Insulation | 6/16/2025 | Corrections Issued | JOSE MACIAS |
| Interior/Exterior Lathing | 6/16/2025 | Approved | JOSE MACIAS |
| Shower Pan | 6/16/2025 | Approved | JOSE MACIAS |
| BUILDING-Rough-Frame | 6/18/2025 | Corrections Issued | JOSE MACIAS |
| Green Building Rough | 6/18/2025 | Approved | JOSE MACIAS |
| HVAC-Rough | 6/18/2025 | Approved | JOSE MACIAS |
| Insulation | 6/18/2025 | Approved | JOSE MACIAS |
| Interior/Exterior Lathing | 6/18/2025 | Approved | JOSE MACIAS |
| Deputy Wood Construction | 6/24/2025 | Conditional Approval | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 7/3/2025 | Approved | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 7/16/2025 | Approved | RONNIE MINDANAO |
| Drywall Nailing | 7/16/2025 | Approved | RONNIE MINDANAO |
| METHANE-Rough | 7/16/2025 | Approved | RONNIE MINDANAO |
| Interior/Exterior Lathing | 8/5/2025 | Approved | RONNIE MINDANAO |
| ELECTRICAL-Rough | 9/9/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| ELECTRICAL-Final | 10/17/2025 | Approved | RONNIE MINDANAO |
| Final | 10/17/2025 | Corrections Issued | RONNIE MINDANAO |
| Green Building Final | 10/17/2025 | Approved | RONNIE MINDANAO |
| HVAC-Final | 10/17/2025 | Approved | RONNIE MINDANAO |
| PLUMBING-Final | 10/17/2025 | Approved | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 10/17/2025 | SGSOV Not Ready | RONNIE MINDANAO |
| Smoke Detectors | 10/17/2025 | Approved | RONNIE MINDANAO |
| Final | 11/7/2025 | Corrections Issued | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 11/7/2025 | SGSOV No Gas | RONNIE MINDANAO |
| Final | 2/20/2026 | Conditional Approval | RONNIE MINDANAO |
| Service/Power Release | 2/20/2026 | Approved | RONNIE MINDANAO |