6141 1/2 W OLYMPIC BLVD 90048

Certificate Information: 6141 1/2 W OLYMPIC BLVD 90048

Application / Permit
24016-20000-23886
Plan Check / Job No.
B24VN10995
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT GARAGE AND STORAGE WITH UNPERMITTED PORTION TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(b)(1)3
Permit Issued
Issued on 2/4/2025
Issuing Office
Current Status
CofO Issued on 2/23/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/26/2024 APPLICANT
Assigned to Plan Check Engineer 8/1/2024 JESSE ARELLANO
Corrections Issued 8/1/2024 JESSE ARELLANO
Building Plans Picked Up 8/8/2024 APPLICANT
Applicant returned to address corrections 2/3/2025 ARAMIK SHAHMIRZAIAN
Plan Check Approved 2/4/2025 NAREG ATARIAN
Issued 2/4/2025 APPLICANT
Permit Finaled 2/23/2026 DEROLD HAUFF
CofO Issued 2/23/2026 DEROLD HAUFF
Permit Finaled 2/23/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/13/2024 WALLIE JONG
Sewer availability Cleared 8/13/2024 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 8/14/2024 WALLIE JONG
City Hist. Cultural Monument Cleared 11/18/2024 RAFAEL FONTES
Historic Resource Verification Cleared 11/18/2024 RAFAEL FONTES
Historic monument Cleared 11/18/2024 RAFAEL FONTES
Redevelopment Project Area Cleared 11/18/2024 RAFAEL FONTES
HPOZ Cleared 1/31/2025 DEBORAH MCGILL

Contact Information

Contractor Owner-Builder       ,
Engineer Standley,, Craig Erick; Lic. No.: C87675 60 VIA CARATAMA      SAN CLEMENTE, CA 92673

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/28/2025 Approved JOSE MACIAS
PLUMBING-Rough 4/14/2025 Partial Approval RONNIE MINDANAO
Sewer 4/14/2025 Approved RONNIE MINDANAO
Underground Mechanical 4/14/2025 Approved RONNIE MINDANAO
Footing/Foundation/Slab 4/18/2025 Corrections Issued RONNIE MINDANAO
Footing/Foundation/Slab 4/21/2025 No Access for Inspection RONNIE MINDANAO
Footing/Foundation/Slab 4/29/2025 Corrections Issued RONNIE MINDANAO
Deputy Drilled-In Anchors 5/6/2025 Conditional Approval RONNIE MINDANAO
Footing/Foundation/Slab 5/6/2025 Approved RONNIE MINDANAO
Pre-Inspection 5/19/2025 Partial Inspection RONNIE MINDANAO
SGSOV-Seismic Gas S/O Valve 6/4/2025 SGSOV Not Ready RONNIE MINDANAO
BUILDING-Rough-Frame 6/11/2025 Corrections Issued WILLIAM SIERRA
ELECTRICAL-Rough 6/11/2025 Approved WILLIAM SIERRA
Green Building Rough 6/11/2025 Corrections Issued WILLIAM SIERRA
HVAC-Rough 6/11/2025 Corrections Issued WILLIAM SIERRA
PLUMBING-Rough 6/11/2025 Approved WILLIAM SIERRA
HVAC-Rough 6/16/2025 Corrections Issued JOSE MACIAS
Insulation 6/16/2025 Corrections Issued JOSE MACIAS
Interior/Exterior Lathing 6/16/2025 Approved JOSE MACIAS
Shower Pan 6/16/2025 Approved JOSE MACIAS
BUILDING-Rough-Frame 6/18/2025 Corrections Issued JOSE MACIAS
Green Building Rough 6/18/2025 Approved JOSE MACIAS
HVAC-Rough 6/18/2025 Approved JOSE MACIAS
Insulation 6/18/2025 Approved JOSE MACIAS
Interior/Exterior Lathing 6/18/2025 Approved JOSE MACIAS
Deputy Wood Construction 6/24/2025 Conditional Approval RONNIE MINDANAO
Floor/Roof Diaphrgm/Shear Wall 7/3/2025 Approved RONNIE MINDANAO
BUILDING-Rough-Frame 7/16/2025 Approved RONNIE MINDANAO
Drywall Nailing 7/16/2025 Approved RONNIE MINDANAO
METHANE-Rough 7/16/2025 Approved RONNIE MINDANAO
Interior/Exterior Lathing 8/5/2025 Approved RONNIE MINDANAO
ELECTRICAL-Rough 9/9/2025 Not Ready for Inspection RONNIE MINDANAO
ELECTRICAL-Final 10/17/2025 Approved RONNIE MINDANAO
Final 10/17/2025 Corrections Issued RONNIE MINDANAO
Green Building Final 10/17/2025 Approved RONNIE MINDANAO
HVAC-Final 10/17/2025 Approved RONNIE MINDANAO
PLUMBING-Final 10/17/2025 Approved RONNIE MINDANAO
SGSOV-Seismic Gas S/O Valve 10/17/2025 SGSOV Not Ready RONNIE MINDANAO
Smoke Detectors 10/17/2025 Approved RONNIE MINDANAO
Final 11/7/2025 Corrections Issued RONNIE MINDANAO
SGSOV-Seismic Gas S/O Valve 11/7/2025 SGSOV No Gas RONNIE MINDANAO
Final 2/20/2026 Conditional Approval RONNIE MINDANAO
Service/Power Release 2/20/2026 Approved RONNIE MINDANAO