7457-7459 N LURLINE AVE 91306

Certificate Information: 7457-7459 N LURLINE AVE 91306

Application / Permit
24016-20000-23247
Plan Check / Job No.
B24VN10279
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan. Convert attached garage to an attached ADU per state law. Work per WFPP.
Permit Issued
Issued on 9/2/2024
Issuing Office
Current Status
CofO Issued on 3/10/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/22/2024 APPLICANT
Assigned to Plan Check Engineer 7/24/2024 DANIEL SMILEY
Corrections Issued 7/25/2024 DANIEL SMILEY
Applicant returned to address corrections 8/19/2024 ZAW HAN
Plan Check Approved 8/30/2024 LUKE GONZALES
Issued 9/2/2024 APPLICANT
CofO in Progress 9/16/2025 ALEXANDER HANDY
Permit Finaled 3/10/2026 JOHN JANSON
CofO Issued 3/10/2026 JOHN JANSON
Permit Finaled 3/10/2026 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 7/31/2024 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 7/31/2024 RYAN CASTRO
Sewer availability Cleared 7/31/2024 RYAN CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DAVID FASTIGGI, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI
ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/19/2025 Conditional Approval ALEXANDER HANDY
Footing/Foundation/Slab 2/24/2025 Corrections Issued ALEXANDER HANDY
PLUMBING-Rough 2/24/2025 Corrections Issued ALEXANDER HANDY
Footing/Foundation/Slab 2/28/2025 Approved KRISTEN CAUSEY
ELECTRICAL-Rough 3/18/2025 Approved JEFFREY HARTLINE
PLUMBING-Rough 3/18/2025 Approved JEFFREY HARTLINE
Shower Pan 3/18/2025 Approved JEFFREY HARTLINE
BUILDING-Rough-Frame 4/3/2025 Approved JEFFREY HARTLINE
Green Building Rough 4/3/2025 Approved JEFFREY HARTLINE
HVAC-Rough 4/3/2025 Approved JEFFREY HARTLINE
Interior/Exterior Lathing 4/3/2025 Partial Approval JEFFREY HARTLINE
Insulation 4/10/2025 Approved SCOTT SOBEL
Drywall Nailing 4/18/2025 Approved JON MCHUGH
Final 7/16/2025 Not Ready for Inspection ALEXANDER HANDY
Green Building Final 7/16/2025 Not Ready for Inspection ALEXANDER HANDY
SGSOV-Seismic Gas S/O Valve 7/16/2025 SGSOV Approved ALEXANDER HANDY
Service/Power Release 7/16/2025 Approved ALEXANDER HANDY
Smoke Detectors 7/16/2025 Approved ALEXANDER HANDY
ELECTRICAL-Final 9/15/2025 Approved ALEXANDER HANDY
Final 9/15/2025 OK to Issue CofO ALEXANDER HANDY
Green Building Final 9/15/2025 Approved ALEXANDER HANDY
HVAC-Final 9/15/2025 Approved ALEXANDER HANDY
PLUMBING-Final 9/15/2025 Approved ALEXANDER HANDY
Special/Order Compliance 9/15/2025 Approved SCOTT SOBEL
Special/Order Compliance 12/31/2025 Corrections Issued HENRY KIM