10477 N REMICK AVE 91331
Certificate Information: 10477 N REMICK AVE 91331
- Application / Permit
- 24016-20000-22952
- Plan Check / Job No.
- B24VN10113
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN. CONVERT EXISTING 499 S.F. ATTACHED GARAGE TO JUNIOR ACCESSORY DWELLING UNIT. ***SEE COMMENTS***
- Permit Issued
- Issued on 4/3/2025
- Issuing Office
- Current Status
- CofO Issued on 6/3/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/18/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/22/2024 | ADAM HEGAZI |
| Corrections Issued | 7/22/2024 | ADAM HEGAZI |
| Plan Check Approved | 3/7/2025 | TSE MING HUANG |
| Issued | 4/3/2025 | APPLICANT |
| CofO in Progress | 5/28/2025 | MICHEL ABAJAN |
| Permit Finaled | 6/3/2025 | RUBEN SALAS |
| Permit Finaled | 6/3/2025 | RUBEN SALAS |
| CofO Issued | 6/3/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 8/2/2024 | KEVIN CHUNG |
| Sewer availability | Cleared | 8/2/2024 | KEVIN CHUNG |
| Eng Process Fee Ord 176,300 | Cleared | 8/5/2024 | KEVIN CHUNG |
Contact Information
| Architect | Tutunjian,, Armen; Lic. No.: C37632 | 1812 W BURBANK BLVD #148 BURBANK, CA 91506 |
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 4/8/2025 | Partial Approval | MICHEL ABAJAN |
| ELECTRICAL-Rough | 4/8/2025 | Approved | MICHEL ABAJAN |
| Green Building Rough | 4/8/2025 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 4/8/2025 | Approved | MICHEL ABAJAN |
| MERV13>=Rough | 4/8/2025 | Approved | MICHEL ABAJAN |
| METHANE-Rough | 4/8/2025 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 4/8/2025 | Approved | MICHEL ABAJAN |
| Shower Pan | 4/8/2025 | Approved | MICHEL ABAJAN |
| Insulation | 4/22/2025 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 4/22/2025 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 5/2/2025 | Approved | LOUIS ESCOTO |
| BUILDING-Rough-Frame | 5/27/2025 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 5/27/2025 | Approved | MICHEL ABAJAN |
| Final | 5/27/2025 | OK to Issue CofO | MICHEL ABAJAN |
| Green Building Final | 5/27/2025 | Approved | MICHEL ABAJAN |
| HVAC-Final | 5/27/2025 | Approved | MICHEL ABAJAN |
| MERV13>=Final | 5/27/2025 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 5/27/2025 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 5/27/2025 | SGSOV Approved | MICHEL ABAJAN |
| Service/Power Release | 5/27/2025 | Approved | MICHEL ABAJAN |
| Smoke Detectors | 5/27/2025 | Approved | MICHEL ABAJAN |