17809 W NORDHOFF ST 91325

Certificate Information: 17809 W NORDHOFF ST 91325

Application / Permit
24016-20000-22744
Plan Check / Job No.
B24VN10037
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN. REC ROOM ADDITION TO (E) SFD WITH ATTACHED GARAGE
Permit Issued
Issued on 1/8/2025
Issuing Office
Current Status
CofO Issued on 6/3/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/19/2024 APPLICANT
Assigned to Plan Check Engineer 7/23/2024 FERNANDO FLORES
Corrections Issued 7/24/2024 FERNANDO FLORES
Applicant returned to address corrections 10/3/2024 FERNANDO FLORES
Applicant returned to address corrections 11/6/2024 SAMUEL GONZALEZ
Plan Check Approved 11/13/2024 ZAW HAN
Issued 1/8/2025 APPLICANT
CofO in Progress 5/27/2025 CHRISTOPHER ROJAS
Permit Finaled 6/3/2025 RUBEN SALAS
CofO Issued 6/3/2025 RUBEN SALAS
Permit Finaled 6/3/2025 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/18/2024 ARMEN SARKISIAN
Roof/Waste drainage to street Cleared 9/18/2024 ARMEN SARKISIAN
Public Works-Highway Ded. Cleared 9/18/2024 ARMEN SARKISIAN
Public Works-Open Permits Cleared 9/18/2024 ARMEN SARKISIAN
Public Works-Sewers Cleared 9/18/2024 ARMEN SARKISIAN

Contact Information

Architect Hong,, Yu Henry; Lic. No.: C31485 4938 STONE RIDGE DRIVE      CHINO HILLS, CA 91709
Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/28/2025 Approved JAVIER RAMOS JR
Footing/Foundation/Slab 1/31/2025 Corrections Issued JAVIER RAMOS JR
Pre-Inspection 1/31/2025 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 3/3/2025 Corrections Issued KEVIN BERBERYAN
Green Building Rough 3/3/2025 Not Ready for Inspection KEVIN BERBERYAN
BUILDING-Rough-Frame 3/10/2025 Corrections Issued JAVIER RAMOS JR
ELECTRICAL-Rough 3/10/2025 Corrections Issued JAVIER RAMOS JR
Footing/Foundation/Slab 3/10/2025 Corrections Issued JAVIER RAMOS JR
BUILDING-Rough-Frame 3/18/2025 Partial Inspection JAVIER RAMOS JR
ELECTRICAL-Rough 3/18/2025 Approved JAVIER RAMOS JR
Footing/Foundation/Slab 3/18/2025 Corrections Issued JAVIER RAMOS JR
Interior/Exterior Lathing 3/18/2025 Corrections Issued JAVIER RAMOS JR
Insulation 3/21/2025 Corrections Issued KEVIN BERBERYAN
Interior/Exterior Lathing 3/26/2025 Corrections Issued GAREN HAYRAPETYAN
BUILDING-Rough-Frame 3/28/2025 Corrections Issued CHRISTOPHER ROJAS
Footing/Foundation/Slab 3/28/2025 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 3/28/2025 Partial Inspection CHRISTOPHER ROJAS
BUILDING-Rough-Frame 4/2/2025 Partial Inspection CHRISTOPHER ROJAS
Green Building Rough 4/2/2025 Approved CHRISTOPHER ROJAS
Insulation 4/2/2025 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 4/2/2025 Approved CHRISTOPHER ROJAS
Drywall Nailing 4/8/2025 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 4/25/2025 Approved GAREN HAYRAPETYAN
Final 4/25/2025 Corrections Issued GAREN HAYRAPETYAN
Green Building Final 4/25/2025 Not Ready for Inspection GAREN HAYRAPETYAN
SGSOV-Seismic Gas S/O Valve 4/25/2025 SGSOV Approved GAREN HAYRAPETYAN
Smoke Detectors 4/25/2025 Approved GAREN HAYRAPETYAN
Final 5/2/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Green Building Final 5/2/2025 Approved CHRISTOPHER ROJAS
ELECTRICAL-Final 5/23/2025 Approved JENNIFER RABUCHIN
Final 5/23/2025 Partial Approval JENNIFER RABUCHIN
HVAC-Final 5/23/2025 Approved JENNIFER RABUCHIN
PLUMBING-Final 5/23/2025 Approved JENNIFER RABUCHIN
Final 5/27/2025 OK to Issue CofO CHRISTOPHER ROJAS