7333 N CAMELLIA AVE 91605

Certificate Information: 7333 N CAMELLIA AVE 91605

Application / Permit
24016-20000-22601
Plan Check / Job No.
B24VN09976
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
interior AND EXTERIOR remodel per plans- remodel bedroom (n)bath,remove wall to enlarge dinning "COMPLY WITH DEPARTMENT ORDER effective date 04/18/2024. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
Permit Issued
Issued on 7/22/2024
Issuing Office
Current Status
Permit Finaled on 10/16/2024

Permit Application Status History

Submitted 7/16/2024 APPLICANT
Assigned to Plan Check Engineer 7/17/2024 SUNMIN LEE
Corrections Issued 7/18/2024 SUNMIN LEE
Plan Check Approved 7/20/2024 CARLOS MONTES
Issued 7/22/2024 APPLICANT
Permit Finaled 10/15/2024 ROBERTO PALACIOS-LOPEZ

Permit Application Clearance Information

No Data Available.

Contact Information

Architect Dembsky,, Amit; Lic. No.: NA30383       ,
Contractor L E A D Enterprises Inc; Lic. No.: 955824-B       ,
Contractor Pearl Remodeling; Lic. No.: 955824-B       ,

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/25/2024 Approved ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 8/6/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 8/6/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Rough 8/6/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 8/6/2024 Approved ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 8/9/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 8/9/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Rough 8/9/2024 Approved ROBERTO PALACIOS-LOPEZ
Drywall Nailing 8/13/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 9/20/2024 Approved JOSE AVILA
Drywall Nailing 9/24/2024 Approved ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 9/24/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Final 9/24/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
PLUMBING-Final 9/24/2024 Approved ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 9/24/2024 SGSOV Not Ready ROBERTO PALACIOS-LOPEZ
Smoke Detectors 9/24/2024 Approved ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 10/3/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Final 10/3/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Final 10/3/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 10/3/2024 SGSOV Not Ready ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 10/9/2024 Approved ROBERT CORNELL
Final 10/15/2024 Permit Finaled ROBERTO PALACIOS-LOPEZ
HVAC-Final 10/15/2024 Approved ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 10/15/2024 SGSOV Approved ROBERTO PALACIOS-LOPEZ