7333 N CAMELLIA AVE 91605
Certificate Information: 7333 N CAMELLIA AVE 91605
- Application / Permit
- 24016-20000-22601
- Plan Check / Job No.
- B24VN09976
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- interior AND EXTERIOR remodel per plans- remodel bedroom (n)bath,remove wall to enlarge dinning "COMPLY WITH DEPARTMENT ORDER effective date 04/18/2024. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
- Permit Issued
- Issued on 7/22/2024
- Issuing Office
- Current Status
- Permit Finaled on 10/16/2024
Permit Application Status History
| Submitted | 7/16/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/17/2024 | SUNMIN LEE |
| Corrections Issued | 7/18/2024 | SUNMIN LEE |
| Plan Check Approved | 7/20/2024 | CARLOS MONTES |
| Issued | 7/22/2024 | APPLICANT |
| Permit Finaled | 10/15/2024 | ROBERTO PALACIOS-LOPEZ |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: NA30383 | , |
| Contractor | L E A D Enterprises Inc; Lic. No.: 955824-B | , |
| Contractor | Pearl Remodeling; Lic. No.: 955824-B | , |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/25/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 8/6/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 8/6/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 8/6/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 8/6/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 8/9/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 8/9/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 8/9/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Drywall Nailing | 8/13/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 9/20/2024 | Approved | JOSE AVILA |
| Drywall Nailing | 9/24/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Final | 9/24/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| HVAC-Final | 9/24/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Final | 9/24/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 9/24/2024 | SGSOV Not Ready | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 9/24/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Final | 10/3/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Final | 10/3/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| HVAC-Final | 10/3/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 10/3/2024 | SGSOV Not Ready | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Final | 10/9/2024 | Approved | ROBERT CORNELL |
| Final | 10/15/2024 | Permit Finaled | ROBERTO PALACIOS-LOPEZ |
| HVAC-Final | 10/15/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 10/15/2024 | SGSOV Approved | ROBERTO PALACIOS-LOPEZ |