7719 N BEN AVE 91605
Certificate Information: 7719 N BEN AVE 91605
- Application / Permit
- 24016-20000-22587
- Plan Check / Job No.
- B24VN09973
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EX DETACHED REC ROOM/ACCESSORY LIVING QUARTER/GARAGE BUILDING INTO (N) 960 SF ACCESSORY DWELLING UNIT PER GCS 65852.2(E)(1)(A). WORK DONE PER ENGINEER DESIGN.
- Permit Issued
- Issued on 10/2/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/17/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/15/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/22/2024 | HAYATO TSUCHIYA |
| Corrections Issued | 7/22/2024 | HAYATO TSUCHIYA |
| Building Plans Picked Up | 7/24/2024 | APPLICANT |
| Applicant returned to address corrections | 8/5/2024 | LUISANGEL VALENZUELA |
| Plan Check Approved | 8/16/2024 | MIROOSH KHACHATOORIAN |
| Issued | 10/2/2024 | APPLICANT |
| CofO in Progress | 11/18/2024 | MATTHEW NELSON |
| Permit Finaled | 12/17/2024 | RUBEN SALAS |
| CofO Issued | 12/17/2024 | RUBEN SALAS |
| Permit Finaled | 12/17/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 8/13/2024 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 8/13/2024 | LEE GUILBEAUX |
| Sewer availability | Cleared | 8/13/2024 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 8/13/2024 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Dike,, Nnadozie; Lic. No.: C87565 | PO BOX 1108 GLENDALE, CA 91209 |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/4/2024 | Conditional Approval | DAVID MATSON |
| Footing/Foundation/Slab | 10/7/2024 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 10/18/2024 | Corrections Issued | MICHEL ABAJAN |
| Green Building Rough | 10/18/2024 | Not Ready for Inspection | MICHEL ABAJAN |
| PLUMBING-Rough | 10/18/2024 | Corrections Issued | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 10/24/2024 | Partial Approval | MATTHEW NELSON |
| Green Building Rough | 10/24/2024 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 10/24/2024 | Approved | MATTHEW NELSON |
| Wood Frame | 10/24/2024 | Not Ready for Inspection | MATTHEW NELSON |
| ELECTRICAL-Rough | 10/30/2024 | Approved | MATTHEW NELSON |
| HVAC-Rough | 10/30/2024 | Approved | MATTHEW NELSON |
| Insulation | 11/1/2024 | Approved | MATTHEW NELSON |
| Drywall Nailing | 11/4/2024 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 11/15/2024 | Approved | MATTHEW NELSON |
| Final | 11/15/2024 | OK to Issue CofO | MATTHEW NELSON |
| Green Building Final | 11/15/2024 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 11/15/2024 | SGSOV Approved | MATTHEW NELSON |
| Smoke Detectors | 11/15/2024 | Approved | MATTHEW NELSON |