9842-9844 N BABBITT AVE 91325
Certificate Information: 9842-9844 N BABBITT AVE 91325
- Application / Permit
- 24016-20000-22493
- Plan Check / Job No.
- B24VN09926
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT REC ROOM/ PORTION OF SFD TO JR ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) AND 65852.22. ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 8/28/2024
- Issuing Office
- Current Status
- CofO Issued on 6/10/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/15/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/22/2024 | JESSE ARELLANO |
| Corrections Issued | 7/23/2024 | JESSE ARELLANO |
| Building Plans Picked Up | 7/24/2024 | APPLICANT |
| Issued | 8/28/2024 | APPLICANT |
| CofO in Progress | 6/9/2026 | CHRISTOPHER ROJAS |
| CofO Issued | 6/10/2026 | RUBEN SALAS |
| Permit Finaled | 6/10/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 7/24/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 7/24/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 7/26/2024 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mayorga,, Jose Aguinaldo; Lic. No.: C50322 | 20457 OREY PL WINNETKA, CA 91306 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 11/14/2025 | Conditional Approval | RAUL OLAGI |
| BUILDING-Rough-Frame | 12/1/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 12/1/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| HVAC-Rough | 12/1/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 12/1/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 12/4/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 12/4/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 12/4/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 12/4/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 12/11/2025 | Partial Approval | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 12/11/2025 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 12/11/2025 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 12/17/2025 | Partial Approval | CHRISTOPHER ROJAS |
| Insulation | 12/17/2025 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 12/22/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 12/22/2025 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 12/22/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 1/2/2026 | Approved | CHRISTOPHER ROJAS |
| Rough-Elec/Plmb/HVAC | 1/2/2026 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Wood Frame | 1/2/2026 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 1/12/2026 | Approved | CHRISTOPHER ROJAS |
| Drywall Nailing | 1/12/2026 | Approved | CHRISTOPHER ROJAS |
| Insulation | 1/12/2026 | Approved | CHRISTOPHER ROJAS |
| Wood Frame | 1/12/2026 | Approved | CHRISTOPHER ROJAS |
| HVAC-Rough | 1/14/2026 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 1/14/2026 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 4/27/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| Final | 4/27/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| HVAC-Final | 4/27/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 4/27/2026 | SGSOV Approved | CHRISTOPHER ROJAS |
| Smoke Detectors | 4/27/2026 | Approved | CHRISTOPHER ROJAS |
| Final | 6/8/2026 | OK to Issue CofO | CHRISTOPHER ROJAS |