22542 W ROSCOE BLVD 91304
Certificate Information: 22542 W ROSCOE BLVD 91304
- Application / Permit
- 24016-20000-22377
- Plan Check / Job No.
- B24VN09885
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- [ePlan] Convert (e) detached garage to ADU. Per CA Govt. Code 65852.2(e)(1)(A). All work per WFPP
- Permit Issued
- Issued on 8/8/2024
- Issuing Office
- Current Status
- Issued on 8/8/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/16/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/19/2024 | ALFREDO JARA |
| Corrections Issued | 7/19/2024 | ALFREDO JARA |
| Applicant returned to address corrections | 8/3/2024 | ALFREDO JARA |
| Plan Check Approved | 8/8/2024 | AMY GUEVARRA |
| Issued | 8/8/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 7/23/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 7/23/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 7/23/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 7/24/2024 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 2/5/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| Excavation/Setback/Form/Re-Bar | 2/5/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| Underground Mechanical | 2/5/2025 | Partial Approval | JEFFREY HARTLINE |
| Excavation/Setback/Form/Re-Bar | 2/21/2025 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 4/1/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| Underground Mechanical | 4/1/2025 | Approved | JEFFREY HARTLINE |
| ELECTRICAL-Rough | 4/22/2025 | Approved | JEFFREY HARTLINE |
| HVAC-Rough | 4/22/2025 | Approved | JEFFREY HARTLINE |
| Floor/Roof Diaphrgm/Shear Wall | 5/1/2025 | Partial Approval | JEFFREY HARTLINE |
| PLUMBING-Rough | 5/1/2025 | Approved | JEFFREY HARTLINE |
| BUILDING-Rough-Frame | 5/21/2025 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Wood Frame | 5/21/2025 | Partial Approval | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 11/13/2025 | Corrections Issued | JEFFREY HARTLINE |
| Green Building Rough | 11/13/2025 | Approved | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 11/13/2025 | Partial Approval | JEFFREY HARTLINE |
| BUILDING-Rough-Frame | 12/23/2025 | Approved | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 12/23/2025 | Approved | JEFFREY HARTLINE |
| Insulation | 1/23/2026 | Approved | JEFFREY HARTLINE |
| Shower Pan | 1/23/2026 | Approved | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 1/30/2026 | Partial Approval | TROY SANDERS |
| Drywall Nailing | 2/6/2026 | Approved | JEFFREY HARTLINE |