8922-8924 N ENFIELD AVE 91325

Certificate Information: 8922-8924 N ENFIELD AVE 91325

Application / Permit
24016-20000-22356
Plan Check / Job No.
B24VN09875
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT ATTACHED GARAGE TO JUNIOR ACCESSORY DWELLING UNIT (423 SQ FT) PER GCS 65852.2(e)(1)(A) and 65852.22.
Permit Issued
Issued on 8/9/2024
Issuing Office
Current Status
CofO Issued on 2/13/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/12/2024 APPLICANT
Assigned to Plan Check Engineer 7/19/2024 JEROME MAGAT PALMA
Corrections Issued 7/23/2024 JEROME MAGAT PALMA
Building Plans Picked Up 7/24/2024 APPLICANT
Plan Check Approved 8/9/2024 GIOVANNY CHAVEZ
Issued 8/9/2024 APPLICANT
CofO in Progress 1/15/2025 JAVIER RAMOS JR
Permit Finaled 2/13/2025 RUBEN SALAS
CofO Issued 2/13/2025 RUBEN SALAS
Permit Finaled 2/13/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 7/23/2024 KEVIN CHUNG
Eng Process Fee Ord 176,300 Cleared 7/23/2024 KEVIN CHUNG
Sewer availability Cleared 7/23/2024 KEVIN CHUNG

Contact Information

Contractor Owner-Builder       ,
Engineer Khatchadourian,, Vicken; Lic. No.: S3141 1221 N CEDAR ST      GLENDALE, CA 92107

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Floor/Roof Diaphrgm/Shear Wall 9/4/2024 Partial Inspection JAVIER RAMOS JR
PLUMBING-Rough 9/4/2024 Partial Approval JAVIER RAMOS JR
Deputy Drilled-In Anchors 9/6/2024 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 9/9/2024 Approved MICHEL ABAJAN
ELECTRICAL-Rough 10/11/2024 Corrections Issued JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 10/11/2024 Partial Inspection JAVIER RAMOS JR
HVAC-Rough 10/11/2024 Partial Inspection JAVIER RAMOS JR
PLUMBING-Rough 10/11/2024 Approved JAVIER RAMOS JR
ELECTRICAL-Rough 10/22/2024 Approved MATTHEW NELSON
HVAC-Rough 10/22/2024 Approved MATTHEW NELSON
Insulation 10/22/2024 Partial Approval MATTHEW NELSON
Interior/Exterior Lathing 10/22/2024 Partial Approval MATTHEW NELSON
BUILDING-Rough-Frame 10/24/2024 Conditional Approval MISAEL ESPARZA
Green Building Rough 10/24/2024 Approved MISAEL ESPARZA
Insulation 10/24/2024 Approved MISAEL ESPARZA
Shower Pan 10/24/2024 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 10/28/2024 Approved MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 10/28/2024 Approved MATTHEW NELSON
Drywall Nailing 11/1/2024 Approved LOUIS ESCOTO
Interior/Exterior Lathing 11/1/2024 Approved LOUIS ESCOTO
Final 12/24/2024 Corrections Issued JACK KARGODORIAN
Green Building Final 12/24/2024 Not Ready for Inspection JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 12/24/2024 SGSOV Approved JACK KARGODORIAN
Smoke Detectors 12/24/2024 Approved JACK KARGODORIAN
ELECTRICAL-Final 1/14/2025 Approved JAVIER RAMOS JR
Final 1/14/2025 OK to Issue CofO JAVIER RAMOS JR
Green Building Final 1/14/2025 Approved JAVIER RAMOS JR
HVAC-Final 1/14/2025 Approved JAVIER RAMOS JR
PLUMBING-Final 1/14/2025 Approved JAVIER RAMOS JR