14019 W HUBBARD ST 91342

Certificate Information: 14019 W HUBBARD ST 91342

Application / Permit
24016-20000-22217
Plan Check / Job No.
B24VN09799
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: Existing Rec room (300 Sq. Ft.) plus existing storage (190 Sq. Ft.) to be converted to new ADU (490 Sq. Ft.) PER GCS 65852.2(e)(1)(A) . WORK PER WFPP
Permit Issued
Issued on 9/10/2024
Issuing Office
Current Status
CofO Issued on 7/22/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/12/2024 APPLICANT
Assigned to Plan Check Engineer 7/17/2024 NGHI SU
Corrections Issued 7/18/2024 NGHI SU
Plan Check Approved 8/21/2024 TSE MING HUANG
Issued 9/10/2024 APPLICANT
CofO in Progress 6/26/2025 KEVIN BERBERYAN
Permit Finaled 7/22/2025 RUBEN SALAS
Permit Finaled 7/22/2025 RUBEN SALAS
CofO Issued 7/22/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 7/20/2024 JOHN LIN
Roof/Waste drainage to street Cleared 7/20/2024 JOHN LIN
Sewer availability Cleared 7/20/2024 JOHN LIN
Eng Process Fee Ord 176,300 Cleared 7/23/2024 JOHN LIN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/10/2025 Corrections Issued KEVIN BERBERYAN
Underground Mechanical 1/10/2025 Approved KEVIN BERBERYAN
Floor/Roof Diaphrgm/Shear Wall 2/7/2025 Partial Approval CHRISTOPHE COCHRAN
Green Building Rough 2/7/2025 Not Ready for Inspection CHRISTOPHE COCHRAN
PLUMBING-Rough 2/7/2025 Corrections Issued CHRISTOPHE COCHRAN
ELECTRICAL-Rough 2/14/2025 Corrections Issued KEVIN BERBERYAN
PLUMBING-Rough 2/14/2025 Not Ready for Inspection KEVIN BERBERYAN
Wood Frame 2/14/2025 Corrections Issued KEVIN BERBERYAN
ELECTRICAL-Rough 2/25/2025 Approved KEVIN BERBERYAN
Insulation 2/25/2025 Not Ready for Inspection KEVIN BERBERYAN
Interior/Exterior Lathing 2/25/2025 Approved KEVIN BERBERYAN
PLUMBING-Rough 2/25/2025 Approved KEVIN BERBERYAN
Wood Frame 2/25/2025 Corrections Issued KEVIN BERBERYAN
Interior/Exterior Lathing 3/3/2025 Approved KEVIN BERBERYAN
Shower Pan 3/3/2025 Corrections Issued KEVIN BERBERYAN
Shower Pan 3/6/2025 Approved KEVIN BERBERYAN
BUILDING-Rough-Frame 4/8/2025 Approved KEVIN BERBERYAN
Green Building Rough 4/8/2025 Approved KEVIN BERBERYAN
Insulation 4/8/2025 Approved KEVIN BERBERYAN
Drywall Nailing 4/11/2025 Approved KEVIN BERBERYAN
Final 6/20/2025 Corrections Issued KEVIN BERBERYAN
Green Building Final 6/20/2025 Not Ready for Inspection KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 6/20/2025 SGSOV Approved KEVIN BERBERYAN
Smoke Detectors 6/20/2025 Approved KEVIN BERBERYAN
Final 6/26/2025 OK to Issue CofO KEVIN BERBERYAN
Green Building Final 6/26/2025 Approved KEVIN BERBERYAN