3233 S CARDIFF AVE 90034

Certificate Information: 3233 S CARDIFF AVE 90034

Application / Permit
24016-20000-22212
Plan Check / Job No.
B24VN09796
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL SINGLE-FAMILY DWELLING WITH NEW 8'-9" X 6'-0" ATTACHED FRONT PATIO COVER
Permit Issued
Issued on 8/15/2024
Issuing Office
Current Status
CofO Issued on 2/24/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/11/2024 APPLICANT
Assigned to Plan Check Engineer 7/18/2024 JESSE ARELLANO
Corrections Issued 7/18/2024 JESSE ARELLANO
Building Plans Picked Up 7/22/2024 APPLICANT
Plan Check Approved 8/1/2024 ALEC MOUSAKHANIAN
Issued 8/15/2024 APPLICANT
CofO in Progress 2/19/2026 WILBER ROSALES
Permit Finaled 2/24/2026 RICHARD STEINBACH
CofO Issued 2/24/2026 RICHARD STEINBACH
Permit Finaled 2/24/2026 RICHARD STEINBACH

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 7/26/2024 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 7/29/2024 DARIN LAM

Contact Information

Contractor Perfect Home Remodeling Inc; Lic. No.: 1088078-B 6946 SEDAN AVENUE      WEST HILLS, CA 91307
Engineer Nirattisai,, Preston; Lic. No.: C85115 28411 ASCENT WAY      SANTA CLARITA, CA 91350

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/5/2024 Corrections Issued ASHLEY THOMPSON
Footing/Foundation/Slab 11/7/2024 Corrections Issued ASHLEY THOMPSON
Footing/Foundation/Slab 11/13/2024 Corrections Issued ASHLEY THOMPSON
Footing/Foundation/Slab 11/18/2024 Approved ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 11/25/2024 Corrections Issued ASHLEY THOMPSON
Green Building Rough 11/25/2024 Not Ready for Inspection ASHLEY THOMPSON
Special/Order Compliance 11/25/2024 Partial Approval REGINA MENDEZ
ELECTRICAL-Rough 11/26/2024 Corrections Issued ARAM AVEDISIAN
PLUMBING-Rough 11/26/2024 Corrections Issued ARAM AVEDISIAN
PLUMBING-Rough 11/27/2024 Corrections Issued ARAM AVEDISIAN
ELECTRICAL-Rough 12/2/2024 Corrections Issued ASHLEY THOMPSON
PLUMBING-Rough 12/2/2024 Corrections Issued ASHLEY THOMPSON
BUILDING-Rough-Frame 12/4/2024 Corrections Issued ASHLEY THOMPSON
ELECTRICAL-Rough 12/4/2024 Not Ready for Inspection ASHLEY THOMPSON
Green Building Rough 12/4/2024 Not Ready for Inspection ASHLEY THOMPSON
PLUMBING-Rough 12/4/2024 Approved ASHLEY THOMPSON
Special/Order Compliance 12/4/2024 Partial Inspection DAVID FEILER
BUILDING-Rough-Frame 12/11/2024 Corrections Issued ASHLEY THOMPSON
Green Building Rough 12/11/2024 Not Ready for Inspection ASHLEY THOMPSON
PLUMBING-Rough 12/11/2024 Approved ASHLEY THOMPSON
BUILDING-Rough-Frame 1/14/2025 Corrections Issued DANIEL VERA
Green Building Rough 1/14/2025 Not Ready for Inspection DANIEL VERA
BUILDING-Rough-Frame 1/23/2025 Not Ready for Inspection MEL KHACHATOURIAN
Green Building Rough 1/23/2025 Not Ready for Inspection MEL KHACHATOURIAN
BUILDING-Rough-Frame 1/29/2025 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Rough 1/29/2025 Approved ARAM AVEDISIAN
Green Building Rough 1/29/2025 Approved ARAM AVEDISIAN
HVAC-Rough 1/29/2025 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 1/29/2025 Partial Approval ARAM AVEDISIAN
Insulation 2/5/2025 Corrections Issued EVAN COOPER
Drywall Nailing 4/2/2025 Approved JAYLIN GRAVITTE
Insulation 4/2/2025 Approved JAYLIN GRAVITTE
Interior/Exterior Lathing 4/2/2025 Approved JAYLIN GRAVITTE
Shower Pan 4/2/2025 Approved JAYLIN GRAVITTE
BUILDING-Rough-Frame 2/13/2026 Approved WILBER ROSALES
ELECTRICAL-Final 2/13/2026 Approved WILBER ROSALES
Final 2/13/2026 OK to Issue CofO WILBER ROSALES
Green Building Final 2/13/2026 Approved WILBER ROSALES
HVAC-Final 2/13/2026 Approved WILBER ROSALES
PLUMBING-Final 2/13/2026 Approved WILBER ROSALES
SGSOV-Seismic Gas S/O Valve 2/13/2026 SGSOV Approved WILBER ROSALES
Smoke Detectors 2/13/2026 Approved WILBER ROSALES