1514 W 20TH ST 90007
Certificate Information: 1514 W 20TH ST 90007
- Application / Permit
- 24016-20000-22042
- Plan Check / Job No.
- B24VN09725
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- VOLUNTARY STRUCTURAL UPGRADE TO EXISTING APARTMENT
- Permit Issued
- Issued on 11/7/2024
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 10/15/2025
Permit Application Status History
| Submitted | 7/10/2024 | APPLICANT |
| Assigned to Zoning Architect | 7/11/2024 | NEVRIK NAVASARTIAN |
| Assigned to Plan Check Engineer | 7/18/2024 | RAPHAEL ROSAS |
| Corrections Issued | 7/22/2024 | RAPHAEL ROSAS |
| Quality Review Completed | 7/24/2024 | STEVEN KIM |
| Building Plans Picked Up | 7/25/2024 | APPLICANT |
| Green Plans Picked Up | 7/25/2024 | APPLICANT |
| Applicant returned to address corrections | 9/26/2024 | RAPHAEL ROSAS |
| Plan Check Approved | 11/7/2024 | RAPHAEL ROSAS |
| Issued | 11/7/2024 | APPLICANT |
| Permit Finaled | 9/30/2025 | JEROME BLACKWOOD |
Permit Application Clearance Information
| CPC | Cleared | 8/6/2024 | BRENNEN OBETO |
| ZA Case | Cleared | 8/6/2024 | BRENNEN OBETO |
| Green Code | Cleared | 9/4/2024 | MICHAEL AYERS |
| Tenant Habitability Plan | Cleared | 10/7/2024 | RICARDO BOHORQUEZ |
| Zoning Plan Check | Cleared | 10/22/2024 | RAPHAEL ROSAS |
Contact Information
| Contractor | One Stop Retrofit; Lic. No.: 1026051-B | 18455 BURBANK BLVD STE 411 TARZANA, CA 91356 |
| Engineer | Alexander,, Andy; Lic. No.: C84086 | 1615 GRAMERCY AVE TORRANCE, CA 90501 |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/27/2024 | Partial Inspection | JEROME BLACKWOOD |
| Floor/Roof Diaphrgm/Shear Wall | 12/9/2024 | Partial Approval | JEROME BLACKWOOD |
| Floor/Roof Diaphrgm/Shear Wall | 12/11/2024 | Partial Approval | JEROME BLACKWOOD |
| Wood Frame | 12/13/2024 | Partial Approval | JEROME BLACKWOOD |
| Wood Frame | 12/17/2024 | Not Ready for Inspection | PAUL BAZERKANIAN |
| Drywall Nailing | 12/19/2024 | Partial Approval | JEROME BLACKWOOD |
| Wood Frame | 12/24/2024 | Partial Approval | JEROME BLACKWOOD |
| Floor/Roof Diaphrgm/Shear Wall | 12/31/2024 | Partial Approval | JEROME BLACKWOOD |
| Wood Frame | 1/6/2025 | Not Ready for Inspection | JEROME BLACKWOOD |
| Wood Frame | 1/15/2025 | Partial Approval | JEROME BLACKWOOD |
| Insulation | 1/16/2025 | Partial Approval | JEROME BLACKWOOD |
| Floor/Roof Diaphrgm/Shear Wall | 1/22/2025 | Partial Approval | PAUL BAZERKANIAN |
| Final | 1/30/2025 | Partial Inspection | JEROME BLACKWOOD |
| Green Building Final | 1/30/2025 | Not Ready for Inspection | JEROME BLACKWOOD |
| SGSOV-Seismic Gas S/O Valve | 1/30/2025 | SGSOV Approved | JEROME BLACKWOOD |
| Smoke Detectors | 1/30/2025 | Approved | JEROME BLACKWOOD |
| Wood Frame | 1/30/2025 | Partial Approval | JEROME BLACKWOOD |
| Floor/Roof Diaphrgm/Shear Wall | 2/6/2025 | Partial Approval | JEROME BLACKWOOD |
| Drywall Nailing | 2/10/2025 | Partial Approval | PAUL BAZERKANIAN |
| Footing/Foundation/Slab | 2/19/2025 | Not Ready for Inspection | CHRISTOPHER BLACKWOOD |
| Footing/Foundation/Slab | 2/20/2025 | Partial Approval | PAUL BAZERKANIAN |
| Interior/Exterior Lathing | 2/27/2025 | Partial Approval | JEROME BLACKWOOD |
| Wood Frame | 2/27/2025 | Partial Approval | JEROME BLACKWOOD |
| Wood Frame | 3/7/2025 | Partial Approval | JEROME BLACKWOOD |
| Drywall Nailing | 3/11/2025 | Partial Approval | PAUL BAZERKANIAN |
| Insulation | 3/18/2025 | Partial Approval | PAUL BAZERKANIAN |
| Wood Frame | 3/18/2025 | Partial Approval | PAUL BAZERKANIAN |
| Wood Frame | 3/26/2025 | Partial Approval | PAUL BAZERKANIAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/1/2025 | Partial Approval | JEROME BLACKWOOD |
| Drywall Nailing | 4/3/2025 | Partial Approval | JEROME BLACKWOOD |
| Insulation | 4/8/2025 | Partial Approval | JEROME BLACKWOOD |
| Wood Frame | 4/8/2025 | Partial Approval | JEROME BLACKWOOD |
| Wood Frame | 4/15/2025 | Partial Approval | JEROME BLACKWOOD |
| Floor/Roof Diaphrgm/Shear Wall | 4/22/2025 | Partial Approval | JEROME BLACKWOOD |
| Insulation | 4/22/2025 | Partial Approval | JEROME BLACKWOOD |
| Interior/Exterior Lathing | 4/28/2025 | Partial Inspection | PAUL BAZERKANIAN |
| Wood Frame | 4/28/2025 | Partial Approval | PAUL BAZERKANIAN |
| Drywall Nailing | 4/30/2025 | Partial Approval | JEROME BLACKWOOD |
| Insulation | 5/6/2025 | Partial Approval | JEROME BLACKWOOD |
| Wood Frame | 5/6/2025 | Partial Approval | JEROME BLACKWOOD |
| Insulation | 5/23/2025 | Not Ready for Inspection | JEROME BLACKWOOD |
| Wood Frame | 5/23/2025 | Corrections Issued | JEROME BLACKWOOD |
| Insulation | 6/10/2025 | Partial Approval | JEROME BLACKWOOD |
| Wood Frame | 6/10/2025 | Partial Approval | JEROME BLACKWOOD |
| Wood Frame | 6/17/2025 | Partial Approval | RAFAEL CORTES |
| Drywall Nailing | 6/18/2025 | Partial Approval | JEROME BLACKWOOD |
| Insulation | 7/8/2025 | Partial Approval | JEROME BLACKWOOD |
| Wood Frame | 7/8/2025 | Partial Approval | JEROME BLACKWOOD |
| Interior/Exterior Lathing | 7/16/2025 | Partial Approval | PAUL BAZERKANIAN |
| Wood Frame | 7/16/2025 | Partial Approval | PAUL BAZERKANIAN |
| Drywall Nailing | 7/22/2025 | Approved | JEROME BLACKWOOD |
| Final | 8/14/2025 | Corrections Issued | JEROME BLACKWOOD |
| Green Building Final | 8/14/2025 | Approved | JEROME BLACKWOOD |
| Final | 9/30/2025 | Permit Finaled | JEROME BLACKWOOD |