6318 N BELMAR AVE 91335

Certificate Information: 6318 N BELMAR AVE 91335

Application / Permit
24016-20000-21906
Plan Check / Job No.
B24VN09653
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan: (E) Detached garage at rear of the lot conversion to an Accessory Dwelling Unit per CA Govt. Code 65852.2(e)(1)(A). All work per WFPP
Permit Issued
Issued on 12/13/2024
Issuing Office
Current Status
CofO Issued on 6/16/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/23/2024 APPLICANT
Assigned to Plan Check Engineer 7/26/2024 EDWIN ESPIN
Corrections Issued 7/28/2024 EDWIN ESPIN
Plan Check Approved 12/9/2024 DAVID CASTILLO
Issued 12/13/2024 APPLICANT
CofO in Progress 6/13/2025 ALEXANDER HANDY
Permit Finaled 6/16/2025 JOHN JANSON
CofO Issued 6/16/2025 JOHN JANSON
Permit Finaled 6/16/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 8/5/2024 CARLOS AGUILERA
Sewer availability Cleared 8/5/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 8/21/2024 CARLOS RAMIREZ
ZI Cleared 9/9/2024 ALEX VELA
Construction within easement Cleared 11/27/2024 THERESA NGUYEN

Contact Information

Contractor Professional Home Remodeling Inc; Lic. No.: 1116137-B       ,

Inspector Information

DAVID FASTIGGI, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI
ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/30/2024 Partial Approval KRISTEN CAUSEY
Deputy Drilled-In Anchors 1/10/2025 Conditional Approval HENRY KIM
Footing/Foundation/Slab 1/10/2025 Approved JOHN COLEMAN
BUILDING-Rough-Frame 1/27/2025 Not Ready for Inspection ALEXANDER HANDY
Green Building Rough 1/27/2025 Not Ready for Inspection ALEXANDER HANDY
Rough-Elec/Plmb/HVAC 1/27/2025 Approved ALEXANDER HANDY
Wood Frame 1/27/2025 Not Ready for Inspection ALEXANDER HANDY
Deputy Drilled-In Anchors 1/30/2025 Conditional Approval ALEXANDER HANDY
BUILDING-Rough-Frame 1/31/2025 Partial Approval ALEXANDER HANDY
Green Building Rough 1/31/2025 Approved ALEXANDER HANDY
Insulation 1/31/2025 Approved ALEXANDER HANDY
Interior/Exterior Lathing 1/31/2025 Partial Approval ALEXANDER HANDY
Drywall Nailing 2/7/2025 Approved ALEXANDER HANDY
Floor/Roof Diaphrgm/Shear Wall 2/7/2025 Approved ALEXANDER HANDY
Interior/Exterior Lathing 2/13/2025 Approved JUAN ALVARADO
Shower Pan 2/13/2025 Approved JUAN ALVARADO
BUILDING-Rough-Frame 6/11/2025 Approved ALEXANDER HANDY
Final 6/11/2025 Corrections Issued ALEXANDER HANDY
Green Building Final 6/11/2025 Approved ALEXANDER HANDY
SGSOV-Seismic Gas S/O Valve 6/11/2025 SGSOV Approved ALEXANDER HANDY
Smoke Detectors 6/11/2025 Approved ALEXANDER HANDY
Final 6/13/2025 OK to Issue CofO ALEXANDER HANDY