12007-12009 N MONOGRAM AVE 91344
Certificate Information: 12007-12009 N MONOGRAM AVE 91344
- Application / Permit
- 24016-20000-21808
- Plan Check / Job No.
- B24VN09584
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN Convert existing attached garage to JADU per state law and storage
- Permit Issued
- Issued on 7/31/2024
- Issuing Office
- Current Status
- CofO Issued on 3/4/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/8/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/12/2024 | MINA HABILI |
| Corrections Issued | 7/13/2024 | MINA HABILI |
| Plan Check Approved | 7/25/2024 | JOSE VELAZQUEZ |
| Issued | 7/31/2024 | APPLICANT |
| CofO in Progress | 2/27/2025 | ROBERT GOLD |
| Permit Finaled | 3/4/2025 | RUBEN SALAS |
| CofO Issued | 3/4/2025 | RUBEN SALAS |
| Permit Finaled | 3/4/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 7/16/2024 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 7/16/2024 | LEE GUILBEAUX |
| Sewer availability | Cleared | 7/16/2024 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 7/16/2024 | LEE GUILBEAUX |
| Grading Pre-Inspection | Cleared | 7/17/2024 | CHARLES POWELL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/23/2024 | Conditional Approval | ROBERT GOLD |
| Excavation/Setback/Form/Re-Bar | 10/25/2024 | Approved | JENNIFER RABUCHIN |
| Light Gage Steel Frame | 10/30/2024 | Not Ready for Inspection | MATTHEW NELSON |
| Underground Mechanical | 10/30/2024 | Partial Approval | MATTHEW NELSON |
| BUILDING-Rough-Frame | 11/6/2024 | Corrections Issued | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 11/6/2024 | Corrections Issued | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 11/21/2024 | Corrections Issued | KEVIN BERBERYAN |
| HVAC-Rough | 11/21/2024 | Corrections Issued | KEVIN BERBERYAN |
| PLUMBING-Rough | 11/21/2024 | Approved | KEVIN BERBERYAN |
| Wood Frame | 11/21/2024 | Conditional Approval | KEVIN BERBERYAN |
| Deputy Wood Construction | 11/22/2024 | Conditional Approval | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 11/26/2024 | Approved | KEVIN BERBERYAN |
| HVAC-Rough | 11/26/2024 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 11/26/2024 | Approved | KEVIN BERBERYAN |
| Wood Frame | 11/26/2024 | Corrections Issued | KEVIN BERBERYAN |
| Insulation | 12/2/2024 | Corrections Issued | MICHAEL CORTEZ |
| BUILDING-Rough-Frame | 12/6/2024 | Corrections Issued | JAVIER RAMOS JR |
| Insulation | 12/6/2024 | Partial Inspection | JAVIER RAMOS JR |
| Drywall Nailing | 12/11/2024 | Conditional Approval | JAVIER RAMOS JR |
| Shower Pan | 12/11/2024 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 1/27/2025 | No Access for Inspection | MICHEL ABAJAN |
| ELECTRICAL-Final | 1/27/2025 | No Access for Inspection | MICHEL ABAJAN |
| Final | 1/27/2025 | No Access for Inspection | MICHEL ABAJAN |
| Green Building Final | 1/27/2025 | No Access for Inspection | MICHEL ABAJAN |
| Green Building Rough | 1/27/2025 | No Access for Inspection | MICHEL ABAJAN |
| HVAC-Final | 1/27/2025 | No Access for Inspection | MICHEL ABAJAN |
| PLUMBING-Final | 1/27/2025 | No Access for Inspection | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 1/27/2025 | SGSOV Not Ready | MICHEL ABAJAN |
| Smoke Detectors | 1/27/2025 | No Access for Inspection | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 2/3/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 2/3/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 2/3/2025 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 2/3/2025 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 2/3/2025 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 2/3/2025 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 2/11/2025 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 2/11/2025 | Approved | JAVIER RAMOS JR |
| Final | 2/11/2025 | Corrections Issued | JAVIER RAMOS JR |
| HVAC-Final | 2/11/2025 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 2/11/2025 | Approved | JAVIER RAMOS JR |
| Final | 2/27/2025 | OK to Issue CofO | ROBERT GOLD |