10740 W ARMINTA ST 91352

Certificate Information: 10740 W ARMINTA ST 91352

Application / Permit
24016-20000-21641
Plan Check / Job No.
B24VN09513
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN: INTERIOR REMODEL TO (E) SINGLE FAMILY DWELLING WITH ATTACHED ACCESSORY DWELLING UNIT UNDER 04014-20000-06199. ALL WORK PER ENGINEERING. NO CHANGE IN FOOTPRINT/ HEIGHT. "COMPLY WITH DEPARTMENT ORDER effective date 03/27/2024. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE" ***SEE COMMENTS***
Permit Issued
Issued on 8/7/2024
Issuing Office
Current Status
Permit Finaled on 8/5/2025

Permit Application Status History

Submitted 7/5/2024 APPLICANT
Assigned to Plan Check Engineer 7/5/2024 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 7/6/2024 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 7/30/2024 SEWADA ZADOORIAN MILAGARDI
Plan Check Approved 8/7/2024 CAROLEAN BASMA
Issued 8/7/2024 APPLICANT
Permit Finaled 8/4/2025 MATTHEW NELSON

Permit Application Clearance Information

Sewer availability Cleared 7/20/2024 JOHN LIN
Eng Process Fee Ord 176,300 Cleared 7/25/2024 JOHN LIN

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

MATTHEW NELSON, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/23/2024 Partial Approval OGANES TARAKHCHYAN
PLUMBING-Rough 10/1/2024 Partial Approval MATTHEW NELSON
Deputy Drilled-In Anchors 10/15/2024 Conditional Approval DAVID MATSON
Deputy Wood Construction 10/15/2024 Conditional Approval DAVID MATSON
Footing/Foundation/Slab 10/17/2024 Approved MATTHEW NELSON
Deputy Wood Construction 12/4/2024 Conditional Approval DAVID MATSON
HVAC-Rough 1/2/2025 Approved MATTHEW NELSON
PLUMBING-Rough 1/2/2025 Approved MATTHEW NELSON
BUILDING-Rough-Frame 1/6/2025 Approved MATTHEW NELSON
ELECTRICAL-Rough 1/6/2025 Approved MATTHEW NELSON
Interior/Exterior Lathing 1/13/2025 Partial Approval MATTHEW NELSON
Insulation 1/24/2025 Approved MATTHEW NELSON
Drywall Nailing 1/29/2025 Approved MATTHEW NELSON
Interior/Exterior Lathing 2/26/2025 Approved MATTHEW NELSON
Final 8/4/2025 Permit Finaled MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 8/4/2025 SGSOV Approved MATTHEW NELSON
Smoke Detectors 8/4/2025 Approved MATTHEW NELSON