8832-8834 N MOONBEAM AVE 91402
Certificate Information: 8832-8834 N MOONBEAM AVE 91402
- Application / Permit
- 24016-20000-21511
- Plan Check / Job No.
- B24VN09454
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN. CONVERT EXISTING ATTACHED GARAGE AND RECREATION ROOM TO ADU IN EXISTING SINGLE FAMILY DEWLLING PER WFPP (Attached ADU Contained in Existing SFD per State Law, CA Govt. Code 65852.2(e)(1)(A))
- Permit Issued
- Issued on 9/3/2024
- Issuing Office
- Current Status
- CofO Issued on 10/31/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/8/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/12/2024 | AUNG SOE |
| Corrections Issued | 7/16/2024 | AUNG SOE |
| Plan Check Approved | 8/14/2024 | AUNG SOE |
| Issued | 9/3/2024 | APPLICANT |
| CofO in Progress | 10/8/2025 | DAVID MATSON |
| Permit Finaled | 10/31/2025 | RUBEN SALAS |
| Permit Finaled | 10/31/2025 | RUBEN SALAS |
| CofO Issued | 10/31/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 7/23/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 7/23/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 7/25/2024 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/26/2024 | Corrections Issued | MATTHEW NELSON |
| Pre-Inspection | 2/10/2025 | Approved | VINCENT HANLEY |
| Underground Mechanical | 2/20/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 2/24/2025 | Partial Approval | JOSE AVILA |
| Deputy Drilled-In Anchors | 3/20/2025 | Conditional Approval | DAVID MATSON |
| Excavation/Setback/Form/Re-Bar | 3/21/2025 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 3/21/2025 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 5/9/2025 | Corrections Issued | MICHEL ABAJAN |
| ELECTRICAL-Rough | 5/9/2025 | Not Ready for Inspection | MICHEL ABAJAN |
| PLUMBING-Rough | 5/9/2025 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 5/20/2025 | Corrections Issued | VINCENT HANLEY |
| ELECTRICAL-Rough | 5/20/2025 | Corrections Issued | VINCENT HANLEY |
| PLUMBING-Rough | 5/20/2025 | Corrections Issued | VINCENT HANLEY |
| BUILDING-Rough-Frame | 6/23/2025 | Partial Approval | VINCENT HANLEY |
| ELECTRICAL-Rough | 6/23/2025 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 6/23/2025 | Approved | VINCENT HANLEY |
| Pre-Inspection | 6/23/2025 | Corrections Issued | VINCENT HANLEY |
| BUILDING-Rough-Frame | 7/11/2025 | Approved | VINCENT HANLEY |
| Green Building Rough | 7/11/2025 | Approved | VINCENT HANLEY |
| HVAC-Rough | 7/11/2025 | Approved | VINCENT HANLEY |
| Insulation | 7/11/2025 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 7/11/2025 | Partial Approval | VINCENT HANLEY |
| Drywall Nailing | 7/25/2025 | Approved | DAVID MATSON |
| Shower Pan | 7/25/2025 | Approved | DAVID MATSON |
| Interior/Exterior Lathing | 8/8/2025 | Approved | LOUIS ESCOTO |
| Shower Pan | 8/8/2025 | Approved | LOUIS ESCOTO |
| ELECTRICAL-Final | 9/9/2025 | Approved | VINCENT HANLEY |
| Final | 9/9/2025 | Corrections Issued | VINCENT HANLEY |
| HVAC-Final | 9/9/2025 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 9/9/2025 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 9/9/2025 | SGSOV Approved | VINCENT HANLEY |
| Smoke Detectors | 9/9/2025 | Approved | VINCENT HANLEY |
| Final | 10/8/2025 | OK to Issue CofO | VINCENT HANLEY |