1244 E 43RD ST 90011

Certificate Information: 1244 E 43RD ST 90011

Application / Permit
24016-20000-21263
Plan Check / Job No.
B24VN09311
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Interior remodel of existing rear studio unit to have open Living/Kitchen area and enlarged bathroom with combo washer dryer unit and closet. Exterior siding will be replaced with stucco. New windows and asphalt shingle reroofing.
Permit Issued
Issued on 9/5/2024
Issuing Office
Current Status
Issued on 9/5/2024

Permit Application Status History

Submitted 7/1/2024 APPLICANT
Assigned to Plan Check Engineer 7/2/2024 PINANK PATEL
Plan Check Approved 7/2/2024 PINANK PATEL
Issued 9/5/2024 APPLICANT

Permit Application Clearance Information

No Data Available.

Contact Information

Architect Maclaury,, Maria Isabel; Lic. No.: NA31836       ,
Contractor R D Mac Construction; Lic. No.: 1070541-B       ,
Engineer Shmeit,, Ayman Ivan; Lic. No.: C93325 9744 MAPLE ST #101      BELLFLOWER, CA 90706

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 10/24/2024 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 10/24/2024 Corrections Issued ALEJANDRO DE ARTOLA
Pre-Inspection 1/21/2025 Approved MICHAEL LEWIS
Pre-Inspection 1/23/2025 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 1/27/2025 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 1/27/2025 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 1/27/2025 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 1/28/2025 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 1/28/2025 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 1/28/2025 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 1/30/2025 No Access for Inspection MICHAEL LEWIS
ELECTRICAL-Rough 1/30/2025 No Access for Inspection MICHAEL LEWIS
PLUMBING-Rough 1/30/2025 No Access for Inspection MICHAEL LEWIS
ELECTRICAL-Rough 2/13/2025 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 2/13/2025 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 2/14/2025 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 2/14/2025 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Rough 2/14/2025 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 2/14/2025 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 4/2/2025 Approved BRENDAN MORELLI
HVAC-Rough 4/2/2025 Conditional Approval BRENDAN MORELLI
Interior/Exterior Lathing 4/2/2025 Partial Approval BRENDAN MORELLI
PLUMBING-Rough 4/2/2025 Approved BRENDAN MORELLI
Excavation/Setback/Form/Re-Bar 6/9/2025 Approved LUIS CASTRO
Deputy Reinf. Concrete 6/11/2025 Partial Approval SCOTT FINNILA
Footing/Foundation/Slab 6/12/2025 Approved LUIS CASTRO
BUILDING-Rough-Frame 6/20/2025 Not Ready for Inspection ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 6/20/2025 Corrections Issued ENRIQUE MIRELES
BUILDING-Rough-Frame 6/27/2025 Not Ready for Inspection BARRY HACHE
Floor/Roof Diaphrgm/Shear Wall 6/27/2025 Not Ready for Inspection BARRY HACHE
BUILDING-Rough-Frame 7/2/2025 Not Ready for Inspection WAYNE REGESTER
Floor/Roof Diaphrgm/Shear Wall 7/2/2025 Not Ready for Inspection WAYNE REGESTER
BUILDING-Rough-Frame 7/10/2025 Partial Approval ALEJANDRO DE ARTOLA
HVAC-Rough 7/10/2025 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 7/23/2025 Approved ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 7/23/2025 Partial Approval ALEJANDRO DE ARTOLA
Insulation 7/23/2025 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 7/24/2025 Approved ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 7/24/2025 Approved ALEJANDRO DE ARTOLA
Drywall Nailing 7/30/2025 Approved MICHAEL LEWIS
Final 1/9/2026 Corrections Issued BARRY HACHE
Smoke Detectors 1/9/2026 Not Ready for Inspection BARRY HACHE
ELECTRICAL-Final 1/16/2026 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 1/16/2026 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 1/16/2026 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 1/27/2026 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 1/27/2026 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 1/27/2026 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 2/18/2026 Corrections Issued ALEJANDRO DE ARTOLA
Final 2/18/2026 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 2/18/2026 SGSOV Not Required ALEJANDRO DE ARTOLA
Smoke Detectors 2/18/2026 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 2/25/2026 Approved ALEJANDRO DE ARTOLA
Final 2/25/2026 Corrections Issued ALEJANDRO DE ARTOLA