9021 N PATRICK AVE 91331

Certificate Information: 9021 N PATRICK AVE 91331

Application / Permit
24016-20000-20920
Plan Check / Job No.
B24VN09123
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A).
Permit Issued
Issued on 7/16/2024
Issuing Office
Current Status
CofO Issued on 1/14/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/27/2024 APPLICANT
Assigned to Plan Check Engineer 7/3/2024 JEROME MAGAT PALMA
Corrections Issued 7/3/2024 JEROME MAGAT PALMA
Building Plans Picked Up 7/5/2024 APPLICANT
Plan Check Approved 7/16/2024 ISIS ARGUETA
Issued 7/16/2024 APPLICANT
CofO in Progress 1/3/2025 VINCENT HANLEY
Permit Finaled 1/14/2025 RUBEN SALAS
CofO Issued 1/14/2025 RUBEN SALAS
Permit Finaled 1/14/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 7/6/2024 BRYAN GODINEZ
Sewer availability Cleared 7/6/2024 BRYAN GODINEZ
Construction near power lines Cleared 7/12/2024 WALTER RAMIREZ
Eng Process Fee Ord 176,300 Cleared 7/15/2024 BRYAN GODINEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/13/2024 Approved GREGG CUMMINGS
Deputy Drilled-In Anchors 8/29/2024 Conditional Approval DAVID MATSON
Footing/Foundation/Slab 9/3/2024 Not Ready for Inspection DAVID MATSON
PLUMBING-Rough 9/3/2024 Corrections Issued DAVID MATSON
Sewer 9/3/2024 Partial Approval DAVID MATSON
Underground Mechanical 9/3/2024 Partial Approval DAVID MATSON
Excavation/Setback/Form/Re-Bar 9/5/2024 Partial Approval JOSE AVILA
PLUMBING-Rough 9/5/2024 Partial Approval JOSE AVILA
Sewer 9/5/2024 Approved JOSE AVILA
Excavation/Setback/Form/Re-Bar 9/9/2024 Approved GREGG CUMMINGS
Footing/Foundation/Slab 9/9/2024 Approved GREGG CUMMINGS
ELECTRICAL-Rough 10/7/2024 Corrections Issued GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 10/7/2024 Partial Approval GREGG CUMMINGS
Green Building Rough 10/7/2024 Approved GREGG CUMMINGS
HVAC-Rough 10/7/2024 Approved GREGG CUMMINGS
MERV13>=Rough 10/7/2024 Approved GREGG CUMMINGS
PLUMBING-Rough 10/7/2024 Corrections Issued GREGG CUMMINGS
BUILDING-Rough-Frame 10/21/2024 Partial Approval GREGG CUMMINGS
ELECTRICAL-Rough 10/21/2024 Approved GREGG CUMMINGS
PLUMBING-Rough 10/21/2024 Approved GREGG CUMMINGS
Insulation 10/29/2024 Approved GREGG CUMMINGS
Interior/Exterior Lathing 10/29/2024 Partial Approval GREGG CUMMINGS
BUILDING-Rough-Frame 11/5/2024 Approved GREGG CUMMINGS
Drywall Nailing 11/18/2024 Approved GREGG CUMMINGS
Interior/Exterior Lathing 11/18/2024 Partial Approval GREGG CUMMINGS
Shower Pan 11/18/2024 Approved GREGG CUMMINGS
ELECTRICAL-Final 12/26/2024 Approved JENNIFER RABUCHIN
Final 12/26/2024 Not Ready for Inspection JENNIFER RABUCHIN
Green Building Final 12/26/2024 Corrections Issued JENNIFER RABUCHIN
HVAC-Final 12/26/2024 Corrections Issued JENNIFER RABUCHIN
MERV13>=Final 12/26/2024 Approved JENNIFER RABUCHIN
PLUMBING-Final 12/26/2024 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 12/26/2024 SGSOV Not Ready JENNIFER RABUCHIN
Smoke Detectors 12/26/2024 Approved JENNIFER RABUCHIN
Final 12/30/2024 Partial Approval VINCENT HANLEY
Green Building Final 12/30/2024 Approved VINCENT HANLEY
HVAC-Final 12/30/2024 Approved VINCENT HANLEY
PLUMBING-Final 12/30/2024 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 12/30/2024 SGSOV Approved VINCENT HANLEY
Final 1/3/2025 OK to Issue CofO VINCENT HANLEY