13687 W BRACKEN ST 91331
Certificate Information: 13687 W BRACKEN ST 91331
- Application / Permit
- 24016-20000-20455
- Plan Check / Job No.
- B24VN08892
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan: Detached 1-Story Garage Conversion to ADU per GCS 65852.2(e)(1)(A). All Work Done per WFPP
- Permit Issued
- Issued on 8/21/2024
- Issuing Office
- Current Status
- CofO Issued on 9/24/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/24/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/28/2024 | DAVID CASTILLO |
| Corrections Issued | 6/29/2024 | DAVID CASTILLO |
| Applicant returned to address corrections | 8/2/2024 | DAVID CASTILLO |
| Plan Check Approved | 8/9/2024 | DAVID CASTILLO |
| Issued | 8/21/2024 | APPLICANT |
| CofO in Progress | 9/18/2025 | VINCENT HANLEY |
| Permit Finaled | 9/24/2025 | RUBEN SALAS |
| CofO Issued | 9/24/2025 | RUBEN SALAS |
| Permit Finaled | 9/24/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 7/20/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 7/20/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 7/22/2024 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/25/2024 | Partial Approval | GREGG CUMMINGS |
| Pre-Inspection | 11/25/2024 | Approved | GREGG CUMMINGS |
| Deputy Drilled-In Anchors | 11/26/2024 | Conditional Approval | DAVID MATSON |
| Footing/Foundation/Slab | 12/5/2024 | Partial Approval | VINCENT HANLEY |
| Deputy Drilled-In Anchors | 12/11/2024 | Conditional Approval | RAUL OLAGI |
| Wood Frame | 12/18/2024 | Corrections Issued | VINCENT HANLEY |
| ELECTRICAL-Rough | 1/13/2025 | Corrections Issued | VINCENT HANLEY |
| HVAC-Rough | 1/13/2025 | Corrections Issued | VINCENT HANLEY |
| Interior/Exterior Lathing | 1/13/2025 | Not Ready for Inspection | VINCENT HANLEY |
| PLUMBING-Rough | 1/13/2025 | Corrections Issued | VINCENT HANLEY |
| BUILDING-Rough-Frame | 1/23/2025 | Approved | VINCENT HANLEY |
| ELECTRICAL-Rough | 1/23/2025 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 1/23/2025 | Approved | VINCENT HANLEY |
| Green Building Rough | 1/23/2025 | Approved | VINCENT HANLEY |
| HVAC-Rough | 1/23/2025 | Approved | VINCENT HANLEY |
| Insulation | 1/23/2025 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 1/23/2025 | Partial Approval | VINCENT HANLEY |
| PLUMBING-Rough | 1/23/2025 | Approved | VINCENT HANLEY |
| Drywall Nailing | 2/7/2025 | Approved | MICHAEL CORTEZ |
| Underground Mechanical | 7/11/2025 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 9/10/2025 | Approved | VINCENT HANLEY |
| Sewer | 9/10/2025 | Approved | VINCENT HANLEY |
| Shower Pan | 9/10/2025 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 9/17/2025 | Approved | VINCENT HANLEY |
| Final | 9/17/2025 | OK to Issue CofO | VINCENT HANLEY |
| HVAC-Final | 9/17/2025 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 9/17/2025 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 9/17/2025 | SGSOV Approved | VINCENT HANLEY |
| Smoke Detectors | 9/17/2025 | Approved | VINCENT HANLEY |