7701-7703 N VARIEL AVE 91304
Certificate Information: 7701-7703 N VARIEL AVE 91304
- Application / Permit
- 24016-20000-20443
- Plan Check / Job No.
- B24VN08881
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: CONVERT (E) ATTACHED GARAGE T0 (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A).
- Permit Issued
- Issued on 7/15/2024
- Issuing Office
- Current Status
- CofO Issued on 6/23/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/24/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/28/2024 | ISIS ARGUETA |
| Corrections Issued | 6/28/2024 | ISIS ARGUETA |
| Plan Check Approved | 7/11/2024 | ISIS ARGUETA |
| Issued | 7/15/2024 | APPLICANT |
| CofO in Progress | 6/3/2025 | ALEXANDER HANDY |
| Permit Finaled | 6/23/2025 | JOHN JANSON |
| CofO Issued | 6/23/2025 | JOHN JANSON |
| Permit Finaled | 6/23/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 7/5/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 7/5/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 7/8/2024 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Shahbaz,, Shant Pierre; Lic. No.: NA93079 | , |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/29/2024 | Conditional Approval | ALEXANDER HANDY |
| Footing/Foundation/Slab | 7/29/2024 | Approved | ARUTYUN MADATYAN |
| Smoke Detectors | 7/29/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Deputy Drilled-In Anchors | 1/21/2025 | Conditional Approval | GEVORK IPCHYAN |
| Footing/Foundation/Slab | 1/23/2025 | Approved | ALEXANDER HANDY |
| PLUMBING-Rough | 1/23/2025 | Partial Approval | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 2/3/2025 | Partial Approval | ALEXANDER HANDY |
| Green Building Rough | 2/3/2025 | Approved | ALEXANDER HANDY |
| Interior/Exterior Lathing | 2/3/2025 | Partial Approval | ALEXANDER HANDY |
| Rough-Elec/Plmb/HVAC | 2/3/2025 | Conditional Approval | ALEXANDER HANDY |
| Gas Test | 2/5/2025 | Approved | JUAN ALVARADO |
| Insulation | 2/5/2025 | Approved | JUAN ALVARADO |
| Drywall Nailing | 2/7/2025 | Approved | JUAN ALVARADO |
| Shower Pan | 2/7/2025 | Approved | JUAN ALVARADO |
| Interior/Exterior Lathing | 2/11/2025 | Approved | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 4/7/2025 | Approved | JUAN ALVARADO |
| Final | 4/7/2025 | Not Ready for Inspection | JUAN ALVARADO |
| Green Building Final | 4/7/2025 | Not Ready for Inspection | JUAN ALVARADO |
| SGSOV-Seismic Gas S/O Valve | 4/7/2025 | SGSOV Not Ready | JUAN ALVARADO |
| Smoke Detectors | 4/7/2025 | Approved | JUAN ALVARADO |
| ELECTRICAL-Final | 6/2/2025 | Approved | ALEXANDER HANDY |
| Final | 6/2/2025 | OK to Issue CofO | ALEXANDER HANDY |
| Green Building Final | 6/2/2025 | Approved | ALEXANDER HANDY |
| HVAC-Final | 6/2/2025 | Approved | ALEXANDER HANDY |
| PLUMBING-Final | 6/2/2025 | Approved | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 6/2/2025 | SGSOV Approved | ALEXANDER HANDY |