7701-7703 N VARIEL AVE 91304

Certificate Information: 7701-7703 N VARIEL AVE 91304

Application / Permit
24016-20000-20443
Plan Check / Job No.
B24VN08881
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: CONVERT (E) ATTACHED GARAGE T0 (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A).
Permit Issued
Issued on 7/15/2024
Issuing Office
Current Status
CofO Issued on 6/23/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/24/2024 APPLICANT
Assigned to Plan Check Engineer 6/28/2024 ISIS ARGUETA
Corrections Issued 6/28/2024 ISIS ARGUETA
Plan Check Approved 7/11/2024 ISIS ARGUETA
Issued 7/15/2024 APPLICANT
CofO in Progress 6/3/2025 ALEXANDER HANDY
Permit Finaled 6/23/2025 JOHN JANSON
CofO Issued 6/23/2025 JOHN JANSON
Permit Finaled 6/23/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 7/5/2024 CARLOS AGUILERA
Sewer availability Cleared 7/5/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 7/8/2024 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Shahbaz,, Shant Pierre; Lic. No.: NA93079       ,

Inspector Information

ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/29/2024 Conditional Approval ALEXANDER HANDY
Footing/Foundation/Slab 7/29/2024 Approved ARUTYUN MADATYAN
Smoke Detectors 7/29/2024 Not Ready for Inspection ARUTYUN MADATYAN
Deputy Drilled-In Anchors 1/21/2025 Conditional Approval GEVORK IPCHYAN
Footing/Foundation/Slab 1/23/2025 Approved ALEXANDER HANDY
PLUMBING-Rough 1/23/2025 Partial Approval ALEXANDER HANDY
BUILDING-Rough-Frame 2/3/2025 Partial Approval ALEXANDER HANDY
Green Building Rough 2/3/2025 Approved ALEXANDER HANDY
Interior/Exterior Lathing 2/3/2025 Partial Approval ALEXANDER HANDY
Rough-Elec/Plmb/HVAC 2/3/2025 Conditional Approval ALEXANDER HANDY
Gas Test 2/5/2025 Approved JUAN ALVARADO
Insulation 2/5/2025 Approved JUAN ALVARADO
Drywall Nailing 2/7/2025 Approved JUAN ALVARADO
Shower Pan 2/7/2025 Approved JUAN ALVARADO
Interior/Exterior Lathing 2/11/2025 Approved ALEXANDER HANDY
BUILDING-Rough-Frame 4/7/2025 Approved JUAN ALVARADO
Final 4/7/2025 Not Ready for Inspection JUAN ALVARADO
Green Building Final 4/7/2025 Not Ready for Inspection JUAN ALVARADO
SGSOV-Seismic Gas S/O Valve 4/7/2025 SGSOV Not Ready JUAN ALVARADO
Smoke Detectors 4/7/2025 Approved JUAN ALVARADO
ELECTRICAL-Final 6/2/2025 Approved ALEXANDER HANDY
Final 6/2/2025 OK to Issue CofO ALEXANDER HANDY
Green Building Final 6/2/2025 Approved ALEXANDER HANDY
HVAC-Final 6/2/2025 Approved ALEXANDER HANDY
PLUMBING-Final 6/2/2025 Approved ALEXANDER HANDY
SGSOV-Seismic Gas S/O Valve 6/2/2025 SGSOV Approved ALEXANDER HANDY