15838-15840 W ECCLES ST 91343

Certificate Information: 15838-15840 W ECCLES ST 91343

Application / Permit
24016-20000-20328
Plan Check / Job No.
B24VN08830
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT ATTACHED GARAGE TO JUNIOR ACCESSORY DWELLING UNIT (379 SQ FT) PER GCS 65852.2(e)(1)(A) and 65852.22. SEE COMMENTS.
Permit Issued
Issued on 9/26/2024
Issuing Office
Current Status
CofO Issued on 2/7/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/21/2024 APPLICANT
Assigned to Plan Check Engineer 6/28/2024 JEROME MAGAT PALMA
Corrections Issued 6/29/2024 JEROME MAGAT PALMA
Building Plans Picked Up 7/1/2024 APPLICANT
Applicant returned to address corrections 8/30/2024 DANIEL ABRAMYAN
Plan Check Approved 9/26/2024 MADISON O'DELL
Issued 9/26/2024 APPLICANT
CofO in Progress 12/24/2024 SALVADOR MARTINEZ
Permit Finaled 2/7/2025 RUBEN SALAS
CofO Issued 2/7/2025 RUBEN SALAS
Permit Finaled 2/7/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 7/2/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 7/2/2024 CARLOS AGUILERA
Sewer availability Cleared 7/2/2024 CARLOS AGUILERA
Construction near power lines Cleared 9/3/2024 WALTER RAMIREZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 10/3/2024 Approved VINCENT HANLEY
Excavation/Setback/Form/Re-Bar 10/9/2024 Approved GAREN HAYRAPETYAN
Footing/Foundation/Slab 10/9/2024 Approved GAREN HAYRAPETYAN
ELECTRICAL-Rough 10/22/2024 Approved SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 10/22/2024 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Rough 10/22/2024 Corrections Issued SALVADOR MARTINEZ
ELECTRICAL-Rough 10/29/2024 Approved SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 10/29/2024 Corrections Issued SALVADOR MARTINEZ
Green Building Rough 10/29/2024 Not Ready for Inspection SALVADOR MARTINEZ
HVAC-Rough 10/29/2024 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Rough 10/29/2024 Approved SALVADOR MARTINEZ
BUILDING-Rough-Frame 11/6/2024 Conditional Approval SALVADOR MARTINEZ
HVAC-Rough 11/6/2024 Approved SALVADOR MARTINEZ
Interior/Exterior Lathing 11/6/2024 Partial Approval SALVADOR MARTINEZ
BUILDING-Rough-Frame 11/8/2024 Approved SALVADOR MARTINEZ
Green Building Rough 11/8/2024 Approved SALVADOR MARTINEZ
Insulation 11/8/2024 Approved SALVADOR MARTINEZ
Drywall Nailing 11/13/2024 Approved SALVADOR MARTINEZ
Sewer 11/13/2024 Approved SALVADOR MARTINEZ
Shower Pan 11/13/2024 Approved SALVADOR MARTINEZ
Interior/Exterior Lathing 11/15/2024 Approved SALVADOR MARTINEZ
ELECTRICAL-Final 12/9/2024 Corrections Issued SALVADOR MARTINEZ
Final 12/9/2024 Corrections Issued SALVADOR MARTINEZ
Green Building Final 12/9/2024 Not Ready for Inspection SALVADOR MARTINEZ
HVAC-Rough 12/9/2024 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Final 12/9/2024 Corrections Issued SALVADOR MARTINEZ
SGSOV-Seismic Gas S/O Valve 12/9/2024 SGSOV No Gas SALVADOR MARTINEZ
Smoke Detectors 12/9/2024 Corrections Issued SALVADOR MARTINEZ
Final 12/13/2024 Corrections Issued SALVADOR MARTINEZ
Green Building Final 12/13/2024 Approved SALVADOR MARTINEZ
Smoke Detectors 12/13/2024 Approved SALVADOR MARTINEZ
Final 12/19/2024 OK to Issue CofO SALVADOR MARTINEZ
Service/Power Release 12/19/2024 Approved SALVADOR MARTINEZ