17430 W GLEDHILL ST 91325

Certificate Information: 17430 W GLEDHILL ST 91325

Application / Permit
24016-20000-20016
Plan Check / Job No.
B24VN08690
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE AND (E) ACCESSORY LIVING QUARTER TO ACCESSORY DWELLING UNIT (960 SF) PER GCS 65852.2(e)(1)(A) AND ADDITION OF (N) 5'-8" X 26'-6" PATIO COVER (230 SF).
Permit Issued
Issued on 8/7/2024
Issuing Office
Current Status
CofO Issued on 5/15/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/18/2024 APPLICANT
Assigned to Plan Check Engineer 6/24/2024 JESSE ARELLANO
Corrections Issued 6/25/2024 JESSE ARELLANO
Building Plans Picked Up 6/26/2024 APPLICANT
Applicant returned to address corrections 7/18/2024 KAMYAR EMAMI
Applicant returned to address corrections 8/1/2024 ALEC MOUSAKHANIAN
Plan Check Approved 8/2/2024 GIOVANNY CHAVEZ
Plan Check Approved 8/7/2024 GIOVANNY CHAVEZ
Issued 8/7/2024 APPLICANT
CofO in Progress 5/6/2025 CHRISTOPHER ROJAS
Permit Finaled 5/15/2025 RUBEN SALAS
CofO Issued 5/15/2025 RUBEN SALAS
Permit Finaled 5/15/2025 RUBEN SALAS

Permit Application Clearance Information

Construction near power lines Cleared 7/9/2024 WALTER RAMIREZ
Address approval Cleared 7/10/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 7/10/2024 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 7/30/2024 CARLOS RAMIREZ
Sewer availability Cleared 8/1/2024 EDGAR ALCARAZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/9/2024 Corrections Issued VINCENT HANLEY
Deputy Drilled-In Anchors 11/5/2024 Conditional Approval JAVIER RAMOS JR
Footing/Foundation/Slab 11/5/2024 Corrections Issued JAVIER RAMOS JR
Interior/Exterior Lathing 11/5/2024 Partial Inspection JAVIER RAMOS JR
Pre-Inspection 11/5/2024 Approved JAVIER RAMOS JR
Wood Frame 11/5/2024 Corrections Issued JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 11/26/2024 Partial Approval JAVIER RAMOS JR
HVAC-Rough 11/26/2024 Approved JAVIER RAMOS JR
Insulation 11/26/2024 Approved JAVIER RAMOS JR
PLUMBING-Rough 11/26/2024 Approved JAVIER RAMOS JR
Wood Frame 11/26/2024 Partial Approval JAVIER RAMOS JR
Drywall Nailing 12/4/2024 Approved LOUIS ESCOTO
Interior/Exterior Lathing 12/4/2024 Approved LOUIS ESCOTO
BUILDING-Rough-Frame 12/31/2024 Approved JAVIER RAMOS JR
ELECTRICAL-Final 12/31/2024 Not Ready for Inspection JAVIER RAMOS JR
Final 12/31/2024 Corrections Issued JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 12/31/2024 Approved JAVIER RAMOS JR
Footing/Foundation/Slab 12/31/2024 Approved JAVIER RAMOS JR
Green Building Final 12/31/2024 Not Ready for Inspection JAVIER RAMOS JR
Green Building Rough 12/31/2024 Approved JAVIER RAMOS JR
Final 3/24/2025 Corrections Issued CHRISTOPHER ROJAS
Green Building Final 3/24/2025 Partial Inspection CHRISTOPHER ROJAS
Final 4/1/2025 Partial Inspection CHRISTOPHER ROJAS
Green Building Final 4/1/2025 Partial Inspection CHRISTOPHER ROJAS
Final 4/10/2025 No Access for Inspection CHRISTOPHER ROJAS
Green Building Final 4/10/2025 No Access for Inspection CHRISTOPHER ROJAS
Final 4/16/2025 Corrections Issued CHRISTOPHER ROJAS
Green Building Final 4/16/2025 Partial Inspection CHRISTOPHER ROJAS
Final 5/5/2025 OK to Issue CofO CHRISTOPHER ROJAS
Green Building Final 5/5/2025 Approved CHRISTOPHER ROJAS