5910 N RIVERTON AVE 91601
Certificate Information: 5910 N RIVERTON AVE 91601
- Application / Permit
- 24016-20000-19945
- Plan Check / Job No.
- B24VN08653
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE & REC ROOM INTO (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A).
- Permit Issued
- Issued on 11/22/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/26/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/18/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/24/2024 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 7/1/2024 | APPLICANT |
| Corrections Issued | 7/15/2024 | ARTIN ZARUKIAN |
| Plan Check Approved | 11/22/2024 | ISIS ARGUETA |
| Issued | 11/22/2024 | APPLICANT |
| No Progress | 12/6/2025 | RAUL OLAGI |
| CofO in Progress | 12/6/2025 | RAUL OLAGI |
| Permit Finaled | 12/26/2025 | RUBEN SALAS |
| CofO Issued | 12/26/2025 | RUBEN SALAS |
| Permit Finaled | 12/26/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 7/20/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 7/20/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 7/22/2024 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 11/3/2024 | TINA MIRANDA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/28/2025 | Approved | JACK KARGODORIAN |
| Pre-Inspection | 6/30/2025 | Partial Approval | JAVIER RAMOS JR |
| Excavation/Setback/Form/Re-Bar | 7/9/2025 | Approved | JOSE AVILA |
| ELECTRICAL-Rough | 7/23/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 7/23/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 7/23/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Special/Order Compliance | 7/23/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 8/4/2025 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 8/4/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 8/4/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Insulation | 8/4/2025 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 8/4/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 8/8/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Drywall Nailing | 8/8/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 8/8/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Insulation | 8/8/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 9/12/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 9/12/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 9/12/2025 | SGSOV Approved | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 9/12/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 9/25/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 9/25/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Final | 11/21/2025 | Conditional Approval | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 11/21/2025 | Approved | ROBERTO PALACIOS-LOPEZ |