20336-20338 W AETNA ST 91367
Certificate Information: 20336-20338 W AETNA ST 91367
- Application / Permit
- 24016-20000-19641
- Plan Check / Job No.
- B24VN08519
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN Convert existing 425 sf attached garage to a JADU PER GCS 65852.2(e)(1)(A) and 65852.22
- Permit Issued
- Issued on 7/28/2024
- Issuing Office
- Current Status
- CofO Issued on 1/15/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/17/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/21/2024 | ZAW HAN |
| Corrections Issued | 6/22/2024 | ZAW HAN |
| Applicant returned to address corrections | 7/19/2024 | ALEXANDER JOO |
| Applicant returned to address corrections | 7/24/2024 | DANIEL SMILEY |
| Plan Check Approved | 7/26/2024 | NGHI SU |
| Issued | 7/28/2024 | APPLICANT |
| CofO in Progress | 1/13/2025 | ALEXANDER HANDY |
| Permit Finaled | 1/15/2025 | JOHN JANSON |
| CofO Issued | 1/15/2025 | JOHN JANSON |
| Permit Finaled | 1/15/2025 | JOHN JANSON |
Permit Application Clearance Information
| ZA Case | Cleared | 6/26/2024 | ASHLEY RODARTE |
| Address approval | Cleared | 6/27/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 6/27/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 6/27/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 6/27/2024 | BIAINA HARITUNIAN |
| Grading Pre-Inspection | Cleared | 6/27/2024 | CHARLES POWELL |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/13/2024 | Approved | ALEXANDER HANDY |
| Wood Frame | 8/26/2024 | Not Ready for Inspection | ALEXANDER HANDY |
| Footing/Foundation/Slab | 8/29/2024 | Not Ready for Inspection | ALEXANDER HANDY |
| Deputy Drilled-In Anchors | 9/9/2024 | Conditional Approval | ARUTYUN MADATYAN |
| Excavation/Setback/Form/Re-Bar | 9/11/2024 | Approved | ARUTYUN MADATYAN |
| Footing/Foundation/Slab | 9/11/2024 | Approved | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 9/11/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| PLUMBING-Rough | 9/11/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Wood Frame | 9/11/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 10/16/2024 | Partial Approval | ALEXANDER HANDY |
| Rough-Elec/Plmb/HVAC | 10/16/2024 | Corrections Issued | ALEXANDER HANDY |
| ELECTRICAL-Rough | 10/21/2024 | Approved | ALEXANDER HANDY |
| HVAC-Rough | 10/21/2024 | Approved | ALEXANDER HANDY |
| PLUMBING-Rough | 10/21/2024 | Approved | ALEXANDER HANDY |
| Drywall Nailing | 10/30/2024 | Approved | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 10/30/2024 | Partial Inspection | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 11/4/2024 | Approved | KRISTEN CAUSEY |
| Shower Pan | 11/4/2024 | Approved | KRISTEN CAUSEY |
| ELECTRICAL-Final | 12/18/2024 | Approved | ALEXANDER HANDY |
| Final | 12/18/2024 | Partial Approval | ALEXANDER HANDY |
| Green Building Final | 12/18/2024 | Approved | ALEXANDER HANDY |
| HVAC-Final | 12/18/2024 | Approved | ALEXANDER HANDY |
| PLUMBING-Final | 12/18/2024 | Approved | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 12/18/2024 | SGSOV Gas Company | ALEXANDER HANDY |
| Service/Power Release | 12/18/2024 | Approved | ALEXANDER HANDY |
| Smoke Detectors | 12/18/2024 | Approved | ALEXANDER HANDY |
| Final | 1/14/2025 | OK to Issue CofO | ALEXANDER HANDY |