6907-6909 N LARAMIE AVE 91306
Certificate Information: 6907-6909 N LARAMIE AVE 91306
- Application / Permit
- 24016-20000-19562
- Plan Check / Job No.
- B24VN08485
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) ATTACHED GARAGE TO JUNIOR ACCESSORY DWELLING UNIT.
- Permit Issued
- Issued on 8/15/2024
- Issuing Office
- Current Status
- CofO Issued on 3/6/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/13/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/20/2024 | ARTIN ZARUKIAN |
| Corrections Issued | 6/22/2024 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 6/24/2024 | APPLICANT |
| Plan Check Approved | 8/13/2024 | ISIS ARGUETA |
| Plan Check Approved | 8/13/2024 | ISIS ARGUETA |
| Issued | 8/15/2024 | APPLICANT |
| CofO in Progress | 2/13/2025 | ALEXANDER HANDY |
| Permit Finaled | 3/6/2025 | JOHN JANSON |
| CofO Issued | 3/6/2025 | JOHN JANSON |
| Permit Finaled | 3/6/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 6/24/2024 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 6/24/2024 | LEE GUILBEAUX |
| Sewer availability | Cleared | 6/24/2024 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 6/24/2024 | LEE GUILBEAUX |
| ZI | Cleared | 6/26/2024 | ALEX VELA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/9/2024 | Conditional Approval | HENRY KIM |
| Footing/Foundation/Slab | 10/9/2024 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Rough | 10/9/2024 | Approved | ARUTYUN MADATYAN |
| Deputy Drilled-In Anchors | 10/18/2024 | Conditional Approval | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 11/18/2024 | Not Ready for Inspection | ALEXANDER HANDY |
| ELECTRICAL-Rough | 11/18/2024 | Corrections Issued | ALEXANDER HANDY |
| Green Building Rough | 11/18/2024 | Not Ready for Inspection | ALEXANDER HANDY |
| HVAC-Rough | 11/18/2024 | Approved | ALEXANDER HANDY |
| PLUMBING-Rough | 11/18/2024 | Approved | ALEXANDER HANDY |
| Wood Frame | 11/18/2024 | Partial Approval | ALEXANDER HANDY |
| ELECTRICAL-Rough | 11/21/2024 | Approved | ALEXANDER HANDY |
| Insulation | 11/21/2024 | Approved | ALEXANDER HANDY |
| Interior/Exterior Lathing | 11/21/2024 | Partial Approval | ALEXANDER HANDY |
| Drywall Nailing | 11/25/2024 | Approved | ALEXANDER HANDY |
| Green Building Rough | 11/25/2024 | Approved | ALEXANDER HANDY |
| Service/Power Release | 11/25/2024 | Not Ready for Inspection | ALEXANDER HANDY |
| Shower Pan | 11/25/2024 | Approved | ALEXANDER HANDY |
| Interior/Exterior Lathing | 12/4/2024 | Approved | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 2/10/2025 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Final | 2/10/2025 | Approved | ALEXANDER HANDY |
| Final | 2/10/2025 | Corrections Issued | ALEXANDER HANDY |
| Green Building Final | 2/10/2025 | Approved | ALEXANDER HANDY |
| HVAC-Final | 2/10/2025 | Approved | ALEXANDER HANDY |
| PLUMBING-Final | 2/10/2025 | Approved | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 2/10/2025 | SGSOV Approved | ALEXANDER HANDY |
| Smoke Detectors | 2/10/2025 | Approved | ALEXANDER HANDY |
| Final | 2/12/2025 | OK to Issue CofO | ALEXANDER HANDY |
| Gas Test | 2/12/2025 | Approved | ALEXANDER HANDY |