8243-8245 N CORBIN AVE 91306

Certificate Information: 8243-8245 N CORBIN AVE 91306

Application / Permit
24016-20000-19384
Plan Check / Job No.
B24VN08380
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT ATTACHED GARAGE TO JUNIOR ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) and 65852.22
Permit Issued
Issued on 3/25/2025
Issuing Office
Valley
Current Status
CofO Issued on 2/26/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/12/2024 APPLICANT
Assigned to Plan Check Engineer 6/19/2024 JEROME MAGAT PALMA
Corrections Issued 6/19/2024 JEROME MAGAT PALMA
Building Plans Picked Up 6/24/2024 APPLICANT
Plan Check Approved 6/27/2024 ALEC MOUSAKHANIAN
Issued 3/25/2025 APPLICANT
CofO in Progress 12/16/2025 ROBERT GOLD
Permit Finaled 2/26/2026 JOHN JANSON
CofO Issued 2/26/2026 JOHN JANSON
Permit Finaled 2/26/2026 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 6/26/2024 BIAINA HARITUNIAN
Sewer availability Cleared 6/26/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 10/10/2024 CHRISTINE KEUSHGUERIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Valencia,, Byron Steve; Lic. No.: C87372 16000 VENTURA BLVD., PH 1203      ENCINO, CA 91436

Inspector Information

ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 6/2/2025 Not Ready for Inspection ALEXANDER HANDY
ELECTRICAL-Rough 6/2/2025 Not Ready for Inspection ALEXANDER HANDY
Footing/Foundation/Slab 6/2/2025 Corrections Issued ALEXANDER HANDY
Green Building Rough 6/2/2025 Not Ready for Inspection ALEXANDER HANDY
PLUMBING-Rough 6/2/2025 Corrections Issued ALEXANDER HANDY
BUILDING-Rough-Frame 6/17/2025 Partial Approval ALEXANDER HANDY
ELECTRICAL-Rough 6/17/2025 Approved ALEXANDER HANDY
Footing/Foundation/Slab 6/17/2025 Approved ALEXANDER HANDY
PLUMBING-Rough 6/17/2025 Approved ALEXANDER HANDY
BUILDING-Rough-Frame 6/24/2025 Partial Approval SCOTT SOBEL
Floor/Roof Diaphrgm/Shear Wall 6/24/2025 Approved SCOTT SOBEL
Interior/Exterior Lathing 6/24/2025 Partial Approval SCOTT SOBEL
BUILDING-Rough-Frame 6/30/2025 Approved SCOTT SOBEL
Green Building Rough 6/30/2025 Approved SCOTT SOBEL
HVAC-Rough 6/30/2025 Approved SCOTT SOBEL
Insulation 6/30/2025 Approved SCOTT SOBEL
Drywall Nailing 7/8/2025 Approved ALEXANDER HANDY
Shower Pan 7/8/2025 Approved ALEXANDER HANDY
BUILDING-Rough-Frame 7/17/2025 Partial Inspection ALEXANDER HANDY
Interior/Exterior Lathing 7/17/2025 Approved ALEXANDER HANDY
BUILDING-Rough-Frame 12/9/2025 Approved ROBERT GOLD
Final 12/9/2025 Corrections Issued ROBERT GOLD
Green Building Final 12/9/2025 Approved ROBERT GOLD
SGSOV-Seismic Gas S/O Valve 12/9/2025 SGSOV Not Ready ROBERT GOLD
Smoke Detectors 12/9/2025 Approved ROBERT GOLD
ELECTRICAL-Final 12/15/2025 Approved ALEXANDER HANDY
Final 12/15/2025 OK to Issue CofO ALEXANDER HANDY
HVAC-Final 12/15/2025 Approved ALEXANDER HANDY
PLUMBING-Final 12/15/2025 Approved ALEXANDER HANDY
SGSOV-Seismic Gas S/O Valve 12/15/2025 SGSOV No Gas ALEXANDER HANDY