15535 W LABRADOR ST 91343

Certificate Information: 15535 W LABRADOR ST 91343

Application / Permit
24016-20000-19334
Plan Check / Job No.
B24VN08343
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
[ePlan] CONVERT EXISTING GARAGE AND WORKSHOP INTO AN ADU ADU CHECKED PER CA GOVT CODE 65852.2(E)(1)(A)
Permit Issued
Issued on 1/24/2025
Issuing Office
Current Status
CofO Issued on 4/16/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/13/2024 APPLICANT
Assigned to Plan Check Engineer 6/18/2024 JOHN MESIAS
Corrections Issued 6/19/2024 JOHN MESIAS
Applicant returned to address corrections 11/20/2024 SUNMIN LEE
Applicant returned to address corrections 12/24/2024 ALEXANDER JOO
Applicant returned to address corrections 1/13/2025 ALEXANDER JOO
Plan Check Approved 1/21/2025 ALEXANDER JOO
Issued 1/24/2025 APPLICANT
CofO in Progress 3/31/2026 VINCENT HANLEY
CofO Issued 4/16/2026 RUBEN SALAS
Permit Finaled 4/16/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 7/6/2024 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 7/6/2024 CARLOS AGUILERA
Sewer availability Cleared 7/6/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 7/9/2024 CARLOS AGUILERA
Construction within easement Cleared 11/14/2024 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Gonzalez,, Fernando Francisco; Lic. No.: NA53256       ,

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/13/2025 Not Ready for Inspection MICHEL ABAJAN
Footing/Foundation/Slab 3/24/2025 Corrections Issued VINCENT HANLEY
Deputy Drilled-In Anchors 4/2/2025 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 4/8/2025 Approved VINCENT HANLEY
Deputy Wood Construction 7/22/2025 Conditional Approval JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 7/23/2025 Corrections Issued VINCENT HANLEY
Sewer 7/23/2025 Approved VINCENT HANLEY
Underground Mechanical 7/23/2025 Approved VINCENT HANLEY
ELECTRICAL-Rough 9/3/2025 Corrections Issued VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 9/3/2025 Approved VINCENT HANLEY
Gas Test 9/3/2025 Corrections Issued VINCENT HANLEY
PLUMBING-Rough 9/3/2025 Corrections Issued VINCENT HANLEY
BUILDING-Rough-Frame 9/22/2025 Approved VINCENT HANLEY
ELECTRICAL-Rough 9/22/2025 Approved VINCENT HANLEY
Green Building Rough 9/22/2025 Approved VINCENT HANLEY
HVAC-Rough 9/22/2025 Approved VINCENT HANLEY
MERV13>=Rough 9/22/2025 Approved VINCENT HANLEY
PLUMBING-Rough 9/22/2025 Approved VINCENT HANLEY
Insulation 9/26/2025 Approved VINCENT HANLEY
Drywall Nailing 10/15/2025 Corrections Issued MICHAEL CORTEZ
Drywall Nailing 10/24/2025 Approved CHRISTOPHER MORFIN
ELECTRICAL-Final 2/20/2026 Approved VINCENT HANLEY
Final 2/20/2026 Corrections Issued VINCENT HANLEY
HVAC-Final 2/20/2026 Approved VINCENT HANLEY
MERV13>=Final 2/20/2026 Approved VINCENT HANLEY
PLUMBING-Final 2/20/2026 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 2/20/2026 SGSOV Approved VINCENT HANLEY
Smoke Detectors 2/20/2026 Approved VINCENT HANLEY
Final 3/31/2026 OK to Issue CofO VINCENT HANLEY