135 1/2 W 51ST ST 90037

Certificate Information: 135 1/2 W 51ST ST 90037

Application / Permit
24016-20000-19261
Plan Check / Job No.
B24VN08294
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan. EXISTING DETACHED GARAGE TO CONVERT IT INTO A NEW ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (C)-(D).
Permit Issued
Issued on 9/3/2024
Issuing Office
Current Status
CofO Issued on 12/23/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/21/2024 APPLICANT
Assigned to Plan Check Engineer 6/27/2024 NGHI SU
Corrections Issued 6/28/2024 NGHI SU
Plan Check Approved 8/13/2024 NGHI SU
Issued 9/3/2024 APPLICANT
CofO in Progress 12/23/2025 LUIS CASTRO
Permit Finaled 12/23/2025 DEROLD HAUFF
CofO Issued 12/23/2025 DEROLD HAUFF
Permit Finaled 12/23/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/1/2024 CHRISTINA BRACO
Sewer availability Cleared 8/1/2024 CHRISTINA BRACO
Eng Process Fee Ord 176,300 Cleared 8/2/2024 CHRISTINA BRACO

Contact Information

Contractor Owner-Builder       ,
Engineer Sandoval,, Martin; Lic. No.: NA56905       ,

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/4/2024 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 12/4/2024 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 12/10/2024 Approved ALEJANDRO DE ARTOLA
PLUMBING-Rough 12/10/2024 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 12/11/2024 Approved ALEJANDRO DE ARTOLA
Underground Mechanical 12/11/2024 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 2/10/2025 Corrections Issued SABAS ALONSO
HVAC-Rough 2/10/2025 Approved SABAS ALONSO
PLUMBING-Rough 2/10/2025 Corrections Issued SABAS ALONSO
ELECTRICAL-Rough 2/13/2025 Approved SABAS ALONSO
PLUMBING-Rough 2/13/2025 Approved SABAS ALONSO
Interior/Exterior Lathing 2/19/2025 Partial Approval ANTHONY RAMOS
Floor/Roof Diaphrgm/Shear Wall 2/25/2025 Corrections Issued JOSE MACIAS
Insulation 2/25/2025 Approved JOSE MACIAS
Drywall Nailing 2/28/2025 Corrections Issued ANTHONY RAMOS
Interior/Exterior Lathing 2/28/2025 Approved ANTHONY RAMOS
Drywall Nailing 3/4/2025 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 3/6/2025 Approved JOSE MACIAS
Green Building Rough 3/6/2025 Approved JOSE MACIAS
Gas Test 5/14/2025 Corrections Issued ALEJANDRO DE ARTOLA
Sewer 5/14/2025 Approved ALEJANDRO DE ARTOLA
Underground Mechanical 5/14/2025 Corrections Issued ALEJANDRO DE ARTOLA
Gas Test 5/16/2025 Approved ALEJANDRO DE ARTOLA
Underground Mechanical 5/16/2025 Approved ALEJANDRO DE ARTOLA
Final 6/13/2025 Corrections Issued WAYNE REGESTER
Green Building Final 6/13/2025 Not Ready for Inspection WAYNE REGESTER
SGSOV-Seismic Gas S/O Valve 6/13/2025 SGSOV Approved WAYNE REGESTER
Smoke Detectors 6/13/2025 Approved WAYNE REGESTER
Final 7/8/2025 Corrections Issued SABAS ALONSO
Green Building Final 7/8/2025 Approved SABAS ALONSO
Final 7/15/2025 Corrections Issued LUIS CASTRO
Final 7/25/2025 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 7/29/2025 Approved LUIS CASTRO
Final 7/29/2025 Conditional Approval LUIS CASTRO
HVAC-Final 7/29/2025 Approved LUIS CASTRO
PLUMBING-Final 7/29/2025 Approved LUIS CASTRO
Final 12/23/2025 OK to Issue CofO LUIS CASTRO