6521 N GENTRY AVE 91606

Certificate Information: 6521 N GENTRY AVE 91606

Application / Permit
24016-20000-19212
Plan Check / Job No.
B24VN08263
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan. CONVERSION OF EXISTING TWO CAR GARAGE INTO ACCESSORY DWELLING UNIT W/ PORCH ADDITION.
Permit Issued
Issued on 8/27/2024
Issuing Office
Current Status
CofO Issued on 6/10/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/11/2024 APPLICANT
Assigned to Plan Check Engineer 6/14/2024 JOHN MESIAS
Corrections Issued 6/15/2024 JOHN MESIAS
Applicant returned to address corrections 6/20/2024 FERNANDO FLORES
Plan Check Approved 8/21/2024 FERNANDO FLORES
Issued 8/27/2024 APPLICANT
CofO in Progress 4/15/2025 ROBERTO PALACIOS-LOPEZ
Permit Finaled 6/10/2025 DANIEL ORRANTE
CofO Issued 6/10/2025 DANIEL ORRANTE
Permit Finaled 6/10/2025 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 6/18/2024 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 6/18/2024 BIAINA HARITUNIAN
Sewer availability Cleared 6/18/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 6/20/2024 BIAINA HARITUNIAN
Construction near power lines Cleared 8/17/2024 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/25/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Excavation/Setback/Form/Re-Bar 10/11/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 10/24/2024 Approved ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 11/14/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 11/14/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Rough 11/14/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 11/14/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 11/18/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 11/18/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 12/4/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Sewer 12/4/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Gas Test 12/24/2024 Approved JOSE AVILA
Sewer 12/24/2024 Approved JOSE AVILA
BUILDING-Rough-Frame 12/27/2024 Partial Approval JOSE AVILA
Underground Mechanical 12/27/2024 Approved JOSE AVILA
Deputy Wood Construction 12/30/2024 Conditional Approval ROBERT GOLD
ELECTRICAL-Rough 1/2/2025 Approved ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 1/2/2025 Approved ROBERTO PALACIOS-LOPEZ
HVAC-Rough 1/2/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 1/2/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 1/2/2025 Approved ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 1/6/2025 Approved ROBERTO PALACIOS-LOPEZ
Green Building Rough 1/6/2025 Approved ROBERTO PALACIOS-LOPEZ
HVAC-Rough 1/6/2025 Approved ROBERTO PALACIOS-LOPEZ
Insulation 1/6/2025 Approved ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 1/6/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
Drywall Nailing 1/10/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Drywall Nailing 1/14/2025 Approved JOSE AVILA
Shower Pan 1/29/2025 Approved LOUIS ESCOTO
Interior/Exterior Lathing 2/3/2025 Approved LOUIS ESCOTO
Final 2/21/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Final 2/21/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 2/21/2025 SGSOV Approved ROBERTO PALACIOS-LOPEZ
Smoke Detectors 2/21/2025 Approved ROBERTO PALACIOS-LOPEZ
Final 3/27/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Final 3/27/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Service/Power Release 3/27/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Final 4/4/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Final 4/4/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 4/10/2025 Approved ROBERTO PALACIOS-LOPEZ
Green Building Final 4/10/2025 Approved ROBERTO PALACIOS-LOPEZ
HVAC-Final 4/10/2025 Approved ROBERTO PALACIOS-LOPEZ
PLUMBING-Final 4/10/2025 Approved ROBERTO PALACIOS-LOPEZ
Final 4/15/2025 OK to Issue CofO ROBERTO PALACIOS-LOPEZ
Service/Power Release 4/15/2025 Approved ROBERTO PALACIOS-LOPEZ