4929-4931 N MARMOL DR 91364

Certificate Information: 4929-4931 N MARMOL DR 91364

Application / Permit
24016-20000-19173
Plan Check / Job No.
B24VN08227
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT EXISTING ATTACHED GARAGE ON FIRST FLOOR OF AN EXISTING TWO-STORY SINGLE FAMILY DWELLING INTO AN ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 10/31/2024
Issuing Office
Current Status
CofO Issued on 4/6/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/11/2024 APPLICANT
Assigned to Plan Check Engineer 6/14/2024 DANIEL ABRAMYAN
Corrections Issued 6/15/2024 DANIEL ABRAMYAN
Plan Check Approved 6/24/2024 ALEC MOUSAKHANIAN
Issued 10/31/2024 APPLICANT
CofO in Progress 1/29/2026 JOHN HAYES
Permit Finaled 4/6/2026 JOHN JANSON
CofO Issued 4/6/2026 JOHN JANSON
Permit Finaled 4/6/2026 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 6/18/2024 BIAINA HARITUNIAN
Sewer availability Cleared 6/18/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 6/20/2024 BIAINA HARITUNIAN
Grading Pre-Inspection Cleared 6/24/2024 ALEC MOUSAKHANIAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN HAYES, (818) 774-4302 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/26/2024 No Access for Inspection KRISTEN CAUSEY
Footing/Foundation/Slab 7/1/2025 Approved JOHN HAYES
Underground Mechanical 7/1/2025 Partial Approval JOHN HAYES
Deputy Drilled-In Anchors 7/8/2025 Conditional Approval JOHN HAYES
ELECTRICAL-Rough 7/22/2025 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 7/22/2025 Partial Approval JOHN HAYES
Wood Frame 7/22/2025 Corrections Issued JOHN HAYES
BUILDING-Rough-Frame 9/4/2025 Corrections Issued JOHN HAYES
ELECTRICAL-Rough 9/4/2025 Not Ready for Inspection JOHN HAYES
Rough-Elec/Plmb/HVAC 9/4/2025 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 9/25/2025 Partial Approval JOHN KIDWELL
ELECTRICAL-Rough 9/25/2025 Approved JOHN KIDWELL
HVAC-Rough 9/25/2025 Approved JOHN KIDWELL
Insulation 9/25/2025 Not Ready for Inspection JOHN KIDWELL
PLUMBING-Rough 9/25/2025 Approved JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 9/26/2025 Corrections Issued ROBERT GOLD
BUILDING-Rough-Frame 10/3/2025 Approved JOHN HAYES
Green Building Rough 10/3/2025 Approved JOHN HAYES
Interior/Exterior Lathing 10/3/2025 Partial Approval JOHN HAYES
Rough-Elec/Plmb/HVAC 10/3/2025 Approved JOHN HAYES
Deputy Wood Construction 10/6/2025 Partial Approval SEAN WIRCH
Insulation 10/7/2025 Corrections Issued SCOTT SOBEL
Shower Pan 10/7/2025 Approved SCOTT SOBEL
Insulation 10/20/2025 Corrections Issued SCOTT SOBEL
Insulation 11/3/2025 Not Ready for Inspection JOHN HAYES
Special/Order Compliance 11/3/2025 Corrections Issued JOHN HAYES
Drywall Nailing 11/12/2025 Approved JOHN KIDWELL
Insulation 11/12/2025 Approved JOHN KIDWELL
Drywall Nailing 11/18/2025 Approved JOHN KIDWELL
Final 1/13/2026 Corrections Issued JOHN HAYES
SGSOV-Seismic Gas S/O Valve 1/13/2026 SGSOV Not Ready JOHN HAYES
Smoke Detectors 1/13/2026 Not Ready for Inspection JOHN HAYES
Final 1/21/2026 OK to Issue CofO JOHN HAYES
SGSOV-Seismic Gas S/O Valve 1/21/2026 SGSOV Approved JOHN HAYES
Smoke Detectors 1/21/2026 Approved JOHN HAYES