11822-11826 W PIERCE ST 91342

Certificate Information: 11822-11826 W PIERCE ST 91342

Application / Permit
24016-20000-19002
Plan Check / Job No.
B24VN08139
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Eplan: Convert attached garage to JADU (481sf) PER STATE LAW.
Permit Issued
Issued on 8/31/2024
Issuing Office
Current Status
CofO Issued on 3/4/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/10/2024 APPLICANT
Assigned to Plan Check Engineer 6/12/2024 KHUONG TRUONG
Corrections Issued 6/13/2024 KHUONG TRUONG
Applicant returned to address corrections 8/2/2024 RICARDO RAMIREZ
Plan Check Approved 8/28/2024 RICARDO RAMIREZ
Issued 8/31/2024 APPLICANT
CofO in Progress 2/20/2025 MICHEL ABAJAN
Permit Finaled 3/4/2025 RUBEN SALAS
Permit Finaled 3/4/2025 RUBEN SALAS
CofO Issued 3/4/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/18/2024 CARLOS RAMIREZ
Sewer availability Cleared 6/18/2024 CARLOS RAMIREZ
Miscellaneous Cleared 6/25/2024 BRENNEN OBETO
Eng Process Fee Ord 176,300 Cleared 6/27/2024 CARLOS RAMIREZ
Grading Pre-Inspection Cleared 7/29/2024 CHARLES POWELL

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/21/2024 Partial Approval MICHEL ABAJAN
Deputy Drilled-In Anchors 10/23/2024 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 10/24/2024 Approved MICHEL ABAJAN
ELECTRICAL-Rough 11/8/2024 Approved MICHEL ABAJAN
HVAC-Rough 11/8/2024 Approved MICHEL ABAJAN
PLUMBING-Rough 11/8/2024 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 11/8/2024 SGSOV Approved MICHEL ABAJAN
Wood Frame 11/8/2024 Approved MICHEL ABAJAN
Insulation 11/13/2024 Approved MICHEL ABAJAN
Interior/Exterior Lathing 11/13/2024 Approved MICHEL ABAJAN
Shower Pan 11/13/2024 Approved MICHEL ABAJAN
Drywall Nailing 11/18/2024 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 2/12/2025 Approved MICHEL ABAJAN
Final 2/12/2025 Corrections Issued MICHEL ABAJAN
Green Building Final 2/12/2025 Approved MICHEL ABAJAN
Green Building Rough 2/12/2025 Approved MICHEL ABAJAN
Smoke Detectors 2/12/2025 Approved MICHEL ABAJAN
Final 2/19/2025 OK to Issue CofO MICHEL ABAJAN
Service/Power Release 2/19/2025 Approved MICHEL ABAJAN