8846 N SWINTON AVE 91343

Certificate Information: 8846 N SWINTON AVE 91343

Application / Permit
24016-20000-18903
Plan Check / Job No.
B24VN08094
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 32'-5"X 15'-0" PATIO COVER ADDITION PER IB P/BC 2023-006 AT REAR. NONSTRUCT INTERIOR REMODEL - REMODEL EX KITCHEN AND REPLACE ONE DOOR AND FIVE WINDOWS PER PLAN.
Permit Issued
Issued on 7/11/2024
Issuing Office
Valley
Current Status
Issued on 7/11/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/7/2024 APPLICANT
Assigned to Plan Check Engineer 6/7/2024 DANIEL ABRAMYAN
Corrections Issued 6/7/2024 DANIEL ABRAMYAN
Applicant returned to address corrections 6/12/2024 HAYATO TSUCHIYA
Issued 7/11/2024 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 6/14/2024 BRYAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 6/20/2024 BRYAN GODINEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 7/25/2024 Not Ready for Inspection RAUL OLAGI
PLUMBING-Rough 7/25/2024 Not Ready for Inspection RAUL OLAGI
Wood Frame 7/25/2024 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 10/28/2024 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Rough 10/28/2024 Corrections Issued SALVADOR MARTINEZ
Pre-Inspection 12/16/2024 Corrections Issued SALVADOR MARTINEZ
BUILDING-Rough-Frame 1/2/2025 Corrections Issued SALVADOR MARTINEZ
ELECTRICAL-Rough 1/2/2025 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Rough 1/2/2025 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Rough 1/24/2025 Corrections Issued SALVADOR MARTINEZ
Deputy Drilled-In Anchors 1/30/2025 Conditional Approval RAUL OLAGI
Footing/Foundation/Slab 2/11/2025 Approved RAUL OLAGI
Special/Order Compliance 2/11/2025 Corrections Issued RAUL OLAGI
Wood Frame 2/18/2025 Partial Approval GAREN HAYRAPETYAN
Insulation 3/7/2025 Not Ready for Inspection LOUIS ESCOTO
Interior/Exterior Lathing 3/7/2025 Not Ready for Inspection LOUIS ESCOTO
BUILDING-Rough-Frame 3/14/2025 Partial Approval SALVADOR MARTINEZ
Insulation 3/14/2025 Partial Approval SALVADOR MARTINEZ
Interior/Exterior Lathing 3/14/2025 Corrections Issued SALVADOR MARTINEZ
ELECTRICAL-Rough 3/18/2025 Partial Approval SALVADOR MARTINEZ
Footing/Foundation/Slab 3/18/2025 Corrections Issued SALVADOR MARTINEZ
HVAC-Rough 3/18/2025 Approved SALVADOR MARTINEZ
PLUMBING-Rough 3/18/2025 Approved SALVADOR MARTINEZ
Footing/Foundation/Slab 3/20/2025 Approved ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 3/24/2025 Approved SALVADOR MARTINEZ
Drywall Nailing 3/28/2025 Approved SALVADOR MARTINEZ
Interior/Exterior Lathing 3/28/2025 Approved SALVADOR MARTINEZ