17230 W SUNBURST ST 91325

Certificate Information: 17230 W SUNBURST ST 91325

Application / Permit
24016-20000-18893
Plan Check / Job No.
B24VN08091
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 32.50' X 8.58' PATIO COVER ADDITION TO THE (E) SINGLE FAMILY DWELLING. TO REPLACE DOOR, INSULATION, INTERIOR WALL, CEILING FINISHES, ROOF FRAMING, EXTERIOR STUCCO PLASTER, TILE ROOFING IN THE (E) SINGLE FAMILY DWELLING.
Permit Issued
Issued on 7/22/2024
Issuing Office
Current Status
CofO Issued on 5/15/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/7/2024 APPLICANT
Assigned to Plan Check Engineer 6/12/2024 GIOVANNY CHAVEZ
Corrections Issued 6/13/2024 GIOVANNY CHAVEZ
Applicant returned to address corrections 7/9/2024 GIOVANNY CHAVEZ
Plan Check Approved 7/19/2024 ALEC MOUSAKHANIAN
Issued 7/22/2024 APPLICANT
CofO in Progress 5/12/2025 CHRISTOPHER ROJAS
Permit Finaled 5/15/2025 RUBEN SALAS
CofO Issued 5/15/2025 RUBEN SALAS
Permit Finaled 5/15/2025 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 7/12/2024 BRYAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 7/16/2024 BRYAN GODINEZ

Contact Information

Contractor H & H Builders And Restoration Inc; Lic. No.: 743872-B       ,
Contractor H & H Restoration; Lic. No.: 743872-B       ,
Engineer Mellor,, Ian; Lic. No.: S5367 4109 CONRAD DR      SPRING VALLEY, CA 91977

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/20/2024 Corrections Issued JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 9/13/2024 Partial Approval JAVIER RAMOS JR
Footing/Foundation/Slab 9/13/2024 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 11/21/2024 Partial Approval JAVIER RAMOS JR
ELECTRICAL-Rough 11/21/2024 Approved JAVIER RAMOS JR
Drywall Nailing 1/28/2025 Approved LOUIS ESCOTO
Insulation 1/28/2025 Approved LOUIS ESCOTO
Interior/Exterior Lathing 1/28/2025 Approved LOUIS ESCOTO
Order to Comply 1/28/2025 OTC Issued LOUIS ESCOTO
BUILDING-Rough-Frame 4/29/2025 Approved CHRISTOPHER ROJAS
Final 4/29/2025 Corrections Issued CHRISTOPHER ROJAS
Green Building Final 4/29/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Green Building Rough 4/29/2025 Approved CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 4/29/2025 SGSOV Approved CHRISTOPHER ROJAS
Smoke Detectors 4/29/2025 Approved CHRISTOPHER ROJAS
Final 5/8/2025 OK to Issue CofO CHRISTOPHER ROJAS
Green Building Final 5/8/2025 Approved CHRISTOPHER ROJAS