10136-10138 N COLLETT AVE 91343
Certificate Information: 10136-10138 N COLLETT AVE 91343
- Application / Permit
- 24016-20000-18738
- Plan Check / Job No.
- B24VN08008
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT ATTACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e)
- Permit Issued
- Issued on 7/9/2024
- Issuing Office
- Current Status
- CofO Issued on 10/24/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/6/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/13/2024 | JEROME MAGAT PALMA |
| Corrections Issued | 6/15/2024 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 6/20/2024 | APPLICANT |
| Plan Check Approved | 7/9/2024 | PINANK PATEL |
| Issued | 7/9/2024 | APPLICANT |
| CofO in Progress | 10/21/2025 | CHRISTOPHER ROJAS |
| Permit Finaled | 10/24/2025 | RUBEN SALAS |
| CofO Issued | 10/24/2025 | RUBEN SALAS |
| Permit Finaled | 10/24/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 6/20/2024 | CHARLES POWELL |
| Address approval | Cleared | 6/24/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 6/24/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 6/25/2024 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Zhang,, Zhiqiang; Lic. No.: M34617 | 410 S SAN GABRIEL BLVD #8 SAN GABRIEL, CA 91776 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/13/2025 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 1/14/2025 | Approved | ROBERT GOLD |
| PLUMBING-Rough | 1/14/2025 | Corrections Issued | ROBERT GOLD |
| Sewer | 1/14/2025 | Partial Inspection | ROBERT GOLD |
| Footing/Foundation/Slab | 1/16/2025 | Approved | MICHEL ABAJAN |
| Sewer | 1/16/2025 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 5/13/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 5/13/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Gas Test | 5/13/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Green Building Rough | 5/13/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Wood Frame | 5/13/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 5/21/2025 | Approved | CHRISTOPHER ROJAS |
| Gas Test | 5/21/2025 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 5/21/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 5/21/2025 | Partial Approval | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 5/28/2025 | Approved | CHRISTOPHER ROJAS |
| Gas Test | 5/28/2025 | Approved | CHRISTOPHER ROJAS |
| Green Building Rough | 5/28/2025 | Approved | CHRISTOPHER ROJAS |
| HVAC-Rough | 5/28/2025 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 5/28/2025 | Approved | CHRISTOPHER ROJAS |
| Insulation | 6/24/2025 | Approved | CHRISTOPHER ROJAS |
| Drywall Nailing | 7/11/2025 | Approved | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 7/11/2025 | Approved | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 7/31/2025 | Approved | CHRISTOPHER ROJAS |
| Final | 10/2/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Green Building Final | 10/2/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| SGSOV-Seismic Gas S/O Valve | 10/2/2025 | SGSOV Approved | NICHOLAS TROWBRIDGE |
| Smoke Detectors | 10/2/2025 | Approved | NICHOLAS TROWBRIDGE |
| Final | 10/17/2025 | OK to Issue CofO | CHRISTOPHER ROJAS |
| Green Building Final | 10/17/2025 | Approved | CHRISTOPHER ROJAS |
| Service/Power Release | 10/17/2025 | Approved | CHRISTOPHER ROJAS |