13147 W ROSCOE BLVD 91352
Certificate Information: 13147 W ROSCOE BLVD 91352
- Application / Permit
- 24016-20000-18717
- Plan Check / Job No.
- B24VN08001
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan: Detached 1-Story Garage Conversion to ADU per and Engineer Design
- Permit Issued
- Issued on 9/16/2024
- Issuing Office
- Current Status
- CofO Issued on 4/29/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/11/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/14/2024 | DAVID CASTILLO |
| Corrections Issued | 6/17/2024 | DAVID CASTILLO |
| Applicant returned to address corrections | 7/12/2024 | ALEXANDER JOO |
| Applicant returned to address corrections | 7/17/2024 | FERNANDO FLORES |
| Plan Check Approved | 9/14/2024 | FERNANDO FLORES |
| Issued | 9/16/2024 | APPLICANT |
| CofO in Progress | 4/24/2025 | VINCENT HANLEY |
| Permit Finaled | 4/29/2025 | RUBEN SALAS |
| CofO Issued | 4/29/2025 | RUBEN SALAS |
| Permit Finaled | 4/29/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 6/29/2024 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 6/29/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 6/29/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 7/2/2024 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 9/12/2024 | OSCAR CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Sivushenka,, Mikita; Lic. No.: C87698 | 22814 DOLOROSA ST WOODLAND HILLS, CA 91367 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/16/2024 | Conditional Approval | DAVID MATSON |
| Excavation/Setback/Form/Re-Bar | 10/17/2024 | Approved | GREGG CUMMINGS |
| Footing/Foundation/Slab | 10/17/2024 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 11/4/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Rough | 11/4/2024 | Corrections Issued | GREGG CUMMINGS |
| Green Building Rough | 11/4/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 11/4/2024 | Corrections Issued | GREGG CUMMINGS |
| Sewer | 11/4/2024 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Rough | 11/8/2024 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 11/8/2024 | Corrections Issued | GREGG CUMMINGS |
| PLUMBING-Rough | 11/8/2024 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 11/19/2024 | Approved | GREGG CUMMINGS |
| Green Building Rough | 11/19/2024 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 11/19/2024 | Approved | GREGG CUMMINGS |
| Insulation | 11/22/2024 | Approved | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 11/22/2024 | Partial Approval | MICHAEL CORTEZ |
| Drywall Nailing | 1/7/2025 | Approved | VINCENT HANLEY |
| Underground Mechanical | 1/7/2025 | Approved | VINCENT HANLEY |
| Gas Test | 1/24/2025 | Approved | VINCENT HANLEY |
| Shower Pan | 1/24/2025 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 2/3/2025 | Partial Approval | JACK KARGODORIAN |
| ELECTRICAL-Final | 4/3/2025 | Corrections Issued | VINCENT HANLEY |
| Final | 4/3/2025 | Not Ready for Inspection | VINCENT HANLEY |
| Green Building Final | 4/3/2025 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 4/3/2025 | Corrections Issued | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 4/3/2025 | SGSOV Approved | VINCENT HANLEY |
| Smoke Detectors | 4/3/2025 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 4/23/2025 | Approved | VINCENT HANLEY |
| Final | 4/23/2025 | OK to Issue CofO | VINCENT HANLEY |
| HVAC-Final | 4/23/2025 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 4/23/2025 | Approved | VINCENT HANLEY |
| Service/Power Release | 4/24/2025 | Approved | VINCENT HANLEY |