11321-11323 N COLLETT AVE 91344
Certificate Information: 11321-11323 N COLLETT AVE 91344
- Application / Permit
- 24016-20000-18640
- Plan Check / Job No.
- B24VN06887
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- <ePLAN> CONVERT 21'6"X20'0" IRREGULAR SHAPED (E) BEDROOM AND BATHROOM TO (N) 374 SQ.FT. JADU. (2 OF 2)
- Permit Issued
- Issued on 9/20/2024
- Issuing Office
- Current Status
- CofO Issued on 9/9/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/16/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/30/2024 | MARVEL DELACRUZ |
| Corrections Issued | 6/6/2024 | MARVEL DELACRUZ |
| Quality Review Completed | 6/6/2024 | OMID HEDAYAT |
| Applicant returned to address corrections | 9/11/2024 | MARVEL DELACRUZ |
| Plan Check Approved | 9/19/2024 | MARVEL DELACRUZ |
| No Progress | 9/19/2024 | MARVEL DELACRUZ |
| Plan Check Approved | 9/19/2024 | MARVEL DELACRUZ |
| Issued | 9/20/2024 | APPLICANT |
| CofO in Progress | 9/2/2025 | CHRISTOPHER ROJAS |
| Permit Finaled | 9/9/2025 | RUBEN SALAS |
| CofO Issued | 9/9/2025 | RUBEN SALAS |
| Permit Finaled | 9/9/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 6/14/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 6/14/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 6/14/2024 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/26/2024 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 3/7/2025 | Corrections Issued | ROBERT GOLD |
| HVAC-Rough | 3/7/2025 | Not Ready for Inspection | ROBERT GOLD |
| PLUMBING-Rough | 3/7/2025 | Corrections Issued | ROBERT GOLD |
| BUILDING-Rough-Frame | 4/2/2025 | Partial Inspection | CHRISTOPHER ROJAS |
| Rough-Elec/Plmb/HVAC | 4/2/2025 | Partial Inspection | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 4/9/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Rough-Elec/Plmb/HVAC | 4/9/2025 | Approved | NICHOLAS TROWBRIDGE |
| Floor/Roof Diaphrgm/Shear Wall | 4/22/2025 | Approved | LOUIS ESCOTO |
| Insulation | 4/22/2025 | Approved | LOUIS ESCOTO |
| Drywall Nailing | 5/2/2025 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 5/19/2025 | Approved | CHRISTOPHER ROJAS |
| Shower Pan | 5/19/2025 | Approved | CHRISTOPHER ROJAS |
| Final | 7/16/2025 | Partial Approval | CHRISTOPHER ROJAS |
| Service/Power Release | 7/16/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Smoke Detectors | 7/16/2025 | Approved | CHRISTOPHER ROJAS |
| Final | 7/22/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Final | 8/20/2025 | No Access for Inspection | CHRISTOPHER ROJAS |
| Pre-Inspection | 8/22/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Final | 8/29/2025 | OK to Issue CofO | CHRISTOPHER ROJAS |
| Service/Power Release | 8/29/2025 | Approved | CHRISTOPHER ROJAS |