747 N HARPER AVE 90046
Certificate Information: 747 N HARPER AVE 90046
- Application / Permit
- 24016-20000-18351
- Plan Check / Job No.
- B24VN07802
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED NONSTRUCT INT REMODEL - CONVERT PORTION OF FIRST FLR OF EX DETACHED 3- CAR GARAGE & ENTIRE 2ND FLR REC RM INTO ACCESSORY DWELLING UNIT PER LAMC 12.22A.33(c) & (d). CONVERT PORTION OF (E) GARAGE TO STORAGE.
- Permit Issued
- Issued on 4/7/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/6/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/4/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/12/2024 | HAYATO TSUCHIYA |
| Corrections Issued | 6/12/2024 | HAYATO TSUCHIYA |
| Building Plans Picked Up | 6/24/2024 | APPLICANT |
| Applicant returned to address corrections | 1/27/2025 | KAMYAR EMAMI |
| Plan Check Approved | 3/21/2025 | ISIS ARGUETA |
| Issued | 4/7/2025 | APPLICANT |
| CofO in Progress | 12/5/2025 | JOSH MEISTER |
| Permit Finaled | 12/6/2025 | DEROLD HAUFF |
| CofO Issued | 12/6/2025 | DEROLD HAUFF |
| Permit Finaled | 12/6/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Sewer availability | Cleared | 6/28/2024 | JESSICA OPINION |
| Eng Process Fee Ord 176,300 | Cleared | 7/8/2024 | JESSICA OPINION |
| Address approval | Cleared | 9/9/2024 | JESSICA OPINION |
| Construction near power lines | Cleared | 12/20/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Gla Puroclean; Lic. No.: 1128637-B | 11523 SHERMAN WAY NORTH HOLLYWOOD, CA 91605 |
| Engineer | Khanjian,, Hovik J; Lic. No.: C51609 | 326 S. SPARKS STREET BURBANK, CA 91506 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Interior/Exterior Lathing | 4/28/2025 | Corrections Issued | WAYNE REGESTER |
| Interior/Exterior Lathing | 4/29/2025 | No Access for Inspection | JOSE MACIAS |
| Wood Frame | 4/29/2025 | No Access for Inspection | JOSE MACIAS |
| BUILDING-Rough-Frame | 5/5/2025 | Not Ready for Inspection | JOSE MACIAS |
| Green Building Final | 5/5/2025 | Not Ready for Inspection | JOSE MACIAS |
| Green Building Rough | 5/5/2025 | Not Ready for Inspection | JOSE MACIAS |
| Interior/Exterior Lathing | 5/5/2025 | Not Ready for Inspection | JOSE MACIAS |
| Pre-Inspection | 5/5/2025 | Corrections Issued | JOSE MACIAS |
| SGSOV-Seismic Gas S/O Valve | 5/5/2025 | SGSOV Not Ready | JOSE MACIAS |
| Smoke Detectors | 5/5/2025 | Not Ready for Inspection | JOSE MACIAS |
| ELECTRICAL-Rough | 9/17/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| HVAC-Rough | 9/17/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| PLUMBING-Rough | 9/17/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| Pre-Inspection | 9/17/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| Wood Frame | 9/17/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| Drywall Nailing | 9/23/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| Insulation | 9/23/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| Interior/Exterior Lathing | 9/23/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| Pre-Inspection | 9/23/2025 | Partial Inspection | RONNIE MINDANAO |
| Pre-Inspection | 10/7/2025 | Approved | JOSH MEISTER |
| BUILDING-Rough-Frame | 10/17/2025 | Approved | JOSH MEISTER |
| ELECTRICAL-Rough | 10/17/2025 | Approved | JOSH MEISTER |
| Green Building Rough | 10/17/2025 | Approved | JOSH MEISTER |
| HVAC-Rough | 10/17/2025 | Approved | JOSH MEISTER |
| Interior/Exterior Lathing | 10/17/2025 | Approved | JOSH MEISTER |
| PLUMBING-Rough | 10/17/2025 | Approved | JOSH MEISTER |
| Drywall Nailing | 10/24/2025 | Approved | ALEX COLIN |
| Insulation | 10/24/2025 | Approved | ALEX COLIN |
| Final | 10/31/2025 | Corrections Issued | RAUL BARAJAS |
| Green Building Final | 10/31/2025 | Not Ready for Inspection | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 10/31/2025 | SGSOV Approved | RAUL BARAJAS |
| Smoke Detectors | 10/31/2025 | Approved | RAUL BARAJAS |
| Final | 11/21/2025 | Corrections Issued | JOSH MEISTER |
| Green Building Final | 11/21/2025 | Not Ready for Inspection | JOSH MEISTER |
| Final | 12/5/2025 | OK to Issue CofO | JOSH MEISTER |
| Green Building Final | 12/5/2025 | Approved | JOSH MEISTER |