1147 1/2 E 43RD PL 90011
Certificate Information: 1147 1/2 E 43RD PL 90011
- Application / Permit
- 24016-20000-18303
- Plan Check / Job No.
- B24VN07789
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan. Convert (E) Detached Garage w/ Storage to (N) ADU per CA Govt.code 65852.2(e)(1)(a)
- Permit Issued
- Issued on 7/29/2024
- Issuing Office
- Current Status
- CofO Issued on 4/8/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/7/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/12/2024 | AMY GUEVARRA |
| Corrections Issued | 6/12/2024 | AMY GUEVARRA |
| Applicant returned to address corrections | 7/15/2024 | AMY GUEVARRA |
| Plan Check Approved | 7/21/2024 | ALFREDO JARA |
| Issued | 7/29/2024 | APPLICANT |
| CofO in Progress | 3/29/2025 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 4/8/2025 | DEROLD HAUFF |
| CofO Issued | 4/8/2025 | DEROLD HAUFF |
| Permit Finaled | 4/8/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/21/2024 | CHRISTINA BRACO |
| Roof/Waste drainage to street | Cleared | 6/21/2024 | CHRISTINA BRACO |
| Sewer availability | Cleared | 6/21/2024 | CHRISTINA BRACO |
| Eng Process Fee Ord 176,300 | Cleared | 7/5/2024 | CHRISTINA BRACO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/21/2024 | Approved | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 8/23/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 8/29/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Deputy Reinf. Concrete | 9/3/2024 | Conditional Approval | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 9/5/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 9/10/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Deputy Drilled-In Anchors | 10/15/2024 | Conditional Approval | ANTHONY RAMOS |
| Deputy Drilled-In Anchors | 11/6/2024 | Conditional Approval | JOSH MEISTER |
| BUILDING-Rough-Frame | 11/8/2024 | Approved | AMIR NAZARIAN |
| ELECTRICAL-Rough | 11/8/2024 | Approved | AMIR NAZARIAN |
| HVAC-Rough | 11/8/2024 | Approved | AMIR NAZARIAN |
| PLUMBING-Rough | 11/8/2024 | Conditional Approval | AMIR NAZARIAN |
| Insulation | 11/12/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 11/12/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Insulation | 11/27/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Shower Pan | 11/27/2024 | Approved | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 11/27/2024 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 12/10/2024 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 12/10/2024 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 12/16/2024 | Approved | ALEJANDRO DE ARTOLA |
| Wood Frame | 12/16/2024 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 12/18/2024 | Corrections Issued | ANTHONY RAMOS |
| Drywall Nailing | 12/19/2024 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 2/6/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 2/6/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Gas Test | 2/6/2025 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 2/6/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 2/6/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 2/13/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 2/13/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 2/13/2025 | Approved | ALEJANDRO DE ARTOLA |
| Final | 2/21/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 2/21/2025 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 2/21/2025 | Approved | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 2/21/2025 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 2/25/2025 | Approved | ALEJANDRO DE ARTOLA |
| Final | 3/28/2025 | OK to Issue CofO | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 3/28/2025 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 3/28/2025 | Approved | ALEJANDRO DE ARTOLA |