1580 W 89TH ST 90047

Certificate Information: 1580 W 89TH ST 90047

Application / Permit
24016-20000-17994
Plan Check / Job No.
B24VN07695
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING DETACHED GARAGE TO NEW ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). WORK DONE PER WFPP DESIGN.
Permit Issued
Issued on 11/13/2024
Issuing Office
Valley
Current Status
Issued on 11/13/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/31/2024 APPLICANT
Assigned to Plan Check Engineer 6/7/2024 JEROME MAGAT PALMA
Corrections Issued 6/8/2024 JEROME MAGAT PALMA
Building Plans Picked Up 6/14/2024 APPLICANT
Plan Check Approved 11/4/2024 MADISON O'DELL
Issued 11/13/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 9/25/2024 DAVID LOPEZ
Sewer availability Cleared 9/25/2024 DAVID LOPEZ
Eng Process Fee Ord 176,300 Cleared 9/26/2024 DAVID LOPEZ
Construction near power lines Cleared 10/9/2024 RIDWAN HARDY

Contact Information

Contractor Yor Construction And Investments Inc; Lic. No.: 978430-B 12135 MIRANDA ST      VALLEY VILLAGE, CA 91607

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/4/2024 Corrections Issued AMIR NAZARIAN
Underground Mechanical 1/6/2025 Approved JOSE MACIAS
Footing/Foundation/Slab 1/21/2025 Corrections Issued MICHAEL LEWIS
Footing/Foundation/Slab 1/24/2025 Partial Approval MICHAEL LEWIS
Footing/Foundation/Slab 2/12/2025 Corrections Issued JOSE MACIAS
Footing/Foundation/Slab 2/14/2025 Approved JOSE MACIAS
Wood Frame 3/7/2025 Corrections Issued JOSE MACIAS
ELECTRICAL-Rough 3/26/2025 Corrections Issued BARRY HACHE
HVAC-Rough 3/26/2025 Not Ready for Inspection BARRY HACHE
Interior/Exterior Lathing 3/26/2025 Not Ready for Inspection BARRY HACHE
PLUMBING-Rough 3/26/2025 Not Ready for Inspection BARRY HACHE
ELECTRICAL-Rough 3/28/2025 Corrections Issued MICHAEL LEWIS
PLUMBING-Rough 3/28/2025 Corrections Issued MICHAEL LEWIS
ELECTRICAL-Rough 4/2/2025 Partial Approval WAYNE REGESTER
HVAC-Rough 4/2/2025 Approved WAYNE REGESTER
PLUMBING-Rough 4/2/2025 Partial Approval WAYNE REGESTER
Wood Frame 4/2/2025 Partial Approval WAYNE REGESTER
ELECTRICAL-Rough 4/4/2025 Partial Inspection WAYNE REGESTER
HVAC-Rough 4/4/2025 Partial Approval WAYNE REGESTER
PLUMBING-Rough 4/4/2025 Partial Approval WAYNE REGESTER
Wood Frame 4/4/2025 Partial Approval WAYNE REGESTER
Insulation 4/8/2025 Approved WAYNE REGESTER
Drywall Nailing 4/14/2025 Approved WAYNE REGESTER
Sewer 4/14/2025 Approved WAYNE REGESTER
Sewer 4/17/2025 Approved WAYNE REGESTER
Shower Pan 4/24/2025 Approved ANTHONY RAMOS
Underground Mechanical 4/24/2025 Approved ANTHONY RAMOS
Interior/Exterior Lathing 5/13/2025 Approved WAYNE REGESTER
BUILDING-Rough-Frame 8/1/2025 Approved WAYNE REGESTER
Final 8/1/2025 Not Ready for Inspection WAYNE REGESTER
Green Building Final 8/1/2025 Corrections Issued WAYNE REGESTER
Green Building Rough 8/1/2025 Approved WAYNE REGESTER
SGSOV-Seismic Gas S/O Valve 8/1/2025 SGSOV Not Ready WAYNE REGESTER
Smoke Detectors 8/1/2025 Not Ready for Inspection WAYNE REGESTER
Final 8/6/2025 Corrections Issued BARRY HACHE
Final 8/8/2025 Corrections Issued JOSE MACIAS
Green Building Final 8/8/2025 Approved JOSE MACIAS
SGSOV-Seismic Gas S/O Valve 8/8/2025 SGSOV Approved JOSE MACIAS
Smoke Detectors 8/8/2025 Approved JOSE MACIAS
Final 8/20/2025 Not Ready for Inspection WAYNE REGESTER
Final 8/22/2025 Not Ready for Inspection WAYNE REGESTER