8500 N BALBOA BLVD 91325

Certificate Information: 8500 N BALBOA BLVD 91325

Application / Permit
24016-20000-17897
Plan Check / Job No.
B24VN07668
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(22) Warehouse
Work Description
ePlan: Strucutural alterations to existing Warehouse building to add 9 dock doors and 1 drive door to Repairing exterior storefront entrance doors and adding one frame door entry, add ramp at docks , all work per engineering
Permit Issued
Issued on 11/25/2024
Issuing Office
Current Status
Issued on 11/25/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/31/2024 APPLICANT
Assigned to Plan Check Engineer 6/6/2024 RARES BODEA
Assigned to Zoning Architect 6/6/2024 NEVRIK NAVASARTIAN
Corrections Issued 6/13/2024 RARES BODEA
Quality Review Completed 6/20/2024 STEVEN KIM
Applicant returned to address corrections 7/25/2024 RARES BODEA
Applicant returned to address corrections 7/31/2024 ARAMIK SHAHMIRZAIAN
Applicant returned to address corrections 10/7/2024 RARES BODEA
Applicant returned to address corrections 10/21/2024 RARES BODEA
Plan Check Approved 10/29/2024 RARES BODEA
Issued 11/25/2024 APPLICANT
Permit Finaled-Status Void 5/28/2025 DEANDRE HOFFMAN
Re-Activate Permit 9/18/2025 DEANDRE HOFFMAN

Permit Application Clearance Information

Green Code Cleared 7/16/2024 MICHAEL AYERS
DAS Clearance Cleared 8/20/2024 Ricardo Ramirez Solis
CPC Cleared 9/3/2024 ALEX VELA
Certificate of Compliance Cleared 9/3/2024 ALEX VELA
Miscellaneous Cleared 9/3/2024 ALEX VELA
Tract Map conditions Cleared 9/3/2024 ALEX VELA
Tract Map conditions Cleared 9/3/2024 ALEX VELA
Metro Rail approval Cleared 9/9/2024 JENNIFER SU
Flood clearance Cleared 9/17/2024 FRANCISCO JIMENEZ
Watercourse Cleared 9/19/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 9/20/2024 RYAN CASTRO
Zoning Plan Check Cleared 9/26/2024 NEVRIK NAVASARTIAN

Contact Information

Architect Jacobson,, Sarah Brady; Lic. No.: C39445 11136 LUCERNE AVE      CULVER CITY, CA 90230
Contractor Clayco Inc; Lic. No.: 714136-B 2199 INNERBELT BUSINESS CENTER   DR    ST LOUIS, MO 63114
Engineer Breaks,, Matthew Calvin; Lic. No.: S6028 5056 TUJUNGA AVE APT 17      NORTH HOLLYWOOD, CA 91601
Engineer Risha,, Janah Adib; Lic. No.: C46811 410 EAST CYPRESS AVE      BURBANK, CA 91501

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/13/2024 Conditional Approval DEANDRE HOFFMAN
Deputy Drilled-In Anchors 12/16/2024 Conditional Approval DEANDRE HOFFMAN
Deputy Drilled-In Anchors 1/13/2025 Partial Approval DEANDRE HOFFMAN
Deputy Steel/Welding 1/13/2025 Conditional Approval DEANDRE HOFFMAN
Reinforced Masonry Frame 1/13/2025 Partial Approval DEANDRE HOFFMAN
Structural Steel Frame 1/13/2025 Partial Approval DEANDRE HOFFMAN
Deputy Drilled-In Anchors 1/22/2025 Conditional Approval DEANDRE HOFFMAN
Deputy Reinf. Concrete 1/22/2025 Conditional Approval DEANDRE HOFFMAN
Excavation/Setback/Form/Re-Bar 1/22/2025 Conditional Approval DEANDRE HOFFMAN
Excavation/Setback/Form/Re-Bar 1/27/2025 Corrections Issued GREGORY POMISH
Footing/Foundation/Slab 1/27/2025 Not Ready for Inspection GREGORY POMISH
Deputy Reinf. Concrete 1/28/2025 Approved DEANDRE HOFFMAN
Excavation/Setback/Form/Re-Bar 1/28/2025 Partial Approval DEANDRE HOFFMAN
Footing/Foundation/Slab 1/28/2025 Partial Approval DEANDRE HOFFMAN
Reinforced Concrete Frame 1/28/2025 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 1/29/2025 Conditional Approval DEANDRE HOFFMAN
Footing/Foundation/Slab 2/3/2025 Partial Approval DEANDRE HOFFMAN
Deputy Reinf. Concrete 2/4/2025 Conditional Approval DEANDRE HOFFMAN
Deputy Reinf. Concrete 2/5/2025 Conditional Approval DEANDRE HOFFMAN
Deputy Drilled-In Anchors 2/11/2025 Conditional Approval DEANDRE HOFFMAN
Deputy Drilled-In Anchors 2/12/2025 Approved DEANDRE HOFFMAN
Footing/Foundation/Slab 2/12/2025 Partial Approval DEANDRE HOFFMAN
Deputy Reinf. Concrete 2/19/2025 Conditional Approval DEANDRE HOFFMAN
Special/Order Compliance 2/20/2025 Corrections Issued DEANDRE HOFFMAN
Deputy Drilled-In Anchors 2/21/2025 Conditional Approval DEANDRE HOFFMAN
Deputy Drilled-In Anchors 2/25/2025 Approved DEANDRE HOFFMAN
Footing/Foundation/Slab 2/25/2025 Partial Approval DEANDRE HOFFMAN
Deputy Reinf. Concrete 2/27/2025 Conditional Approval KENNETH ROBERTS
Deputy Reinf. Concrete 3/3/2025 Approved DEANDRE HOFFMAN
Excavation/Setback/Form/Re-Bar 3/3/2025 Partial Approval DEANDRE HOFFMAN
Deputy Reinf. Concrete 3/4/2025 Conditional Approval DEANDRE HOFFMAN
Excavation/Setback/Form/Re-Bar 3/6/2025 Partial Approval DEANDRE HOFFMAN
Deputy Drilled-In Anchors 3/7/2025 Approved DEANDRE HOFFMAN
Deputy Reinf. Concrete 3/7/2025 Conditional Approval DEANDRE HOFFMAN
Deputy Reinf. Concrete 3/10/2025 Conditional Approval DEANDRE HOFFMAN
Deputy Reinf. Concrete 4/1/2025 Conditional Approval DEANDRE HOFFMAN
Deputy Reinf. Concrete 4/4/2025 Conditional Approval DEANDRE HOFFMAN
Footing/Foundation/Slab 4/22/2025 Partial Approval DEANDRE HOFFMAN
Deputy Reinf. Concrete 4/23/2025 Conditional Approval DEANDRE HOFFMAN
Deputy Drilled-In Anchors 4/29/2025 Conditional Approval DEANDRE HOFFMAN
Deputy Reinf. Concrete 4/29/2025 Conditional Approval DEANDRE HOFFMAN
Excavation/Setback/Form/Re-Bar 4/30/2025 Approved DEANDRE HOFFMAN
Deputy Reinf. Concrete 5/1/2025 Conditional Approval DEANDRE HOFFMAN
Final 5/14/2025 Partial Inspection DEANDRE HOFFMAN
Green Building Final 5/14/2025 Approved DEANDRE HOFFMAN
SGSOV-Seismic Gas S/O Valve 5/14/2025 SGSOV Approved DEANDRE HOFFMAN
Smoke Detectors 5/14/2025 Approved DEANDRE HOFFMAN
Final 5/16/2025 Not Ready for Inspection BRIAN KELLY
Final 5/20/2025 Not Ready for Inspection DEANDRE HOFFMAN
Final 5/28/2025 Not Ready for Inspection DEANDRE HOFFMAN
Final 12/8/2025 Not Ready for Inspection DEANDRE HOFFMAN