7738-7740 N AMPERE AVE 91605

Certificate Information: 7738-7740 N AMPERE AVE 91605

Application / Permit
24016-20000-17611
Plan Check / Job No.
B24VN07552
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: Convert (e) att. 2-car garage to JADU per CA Govt. Code 65852.2(e)(1)(A) per WFPP
Permit Issued
Issued on 10/21/2024
Issuing Office
Current Status
CofO Issued on 1/2/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/29/2024 APPLICANT
Assigned to Plan Check Engineer 6/3/2024 REZA HAGHIGHAT
Corrections Issued 6/3/2024 REZA HAGHIGHAT
Plan Check Approved 10/20/2024 REZA HAGHIGHAT
Issued 10/21/2024 APPLICANT
CofO in Progress 12/22/2025 VINCENT HANLEY
Permit Finaled 1/2/2026 RUBEN SALAS
CofO Issued 1/2/2026 RUBEN SALAS
Permit Finaled 1/2/2026 RUBEN SALAS

Permit Application Clearance Information

Construction near power lines Cleared 9/7/2024 RIDWAN HARDY
Address approval Cleared 9/17/2024 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 9/17/2024 RYAN CASTRO
Sewer availability Cleared 9/17/2024 RYAN CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/4/2025 Approved VINCENT HANLEY
Footing/Foundation/Slab 4/16/2025 Corrections Issued VINCENT HANLEY
PLUMBING-Rough 4/16/2025 Corrections Issued VINCENT HANLEY
Excavation/Setback/Form/Re-Bar 5/1/2025 Approved VINCENT HANLEY
Footing/Foundation/Slab 5/1/2025 Approved VINCENT HANLEY
PLUMBING-Rough 5/1/2025 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 7/8/2025 Partial Approval VINCENT HANLEY
ELECTRICAL-Rough 7/8/2025 Approved VINCENT HANLEY
Green Building Rough 7/8/2025 Approved VINCENT HANLEY
HVAC-Rough 7/8/2025 Approved VINCENT HANLEY
PLUMBING-Rough 7/8/2025 Approved VINCENT HANLEY
BUILDING-Rough-Frame 8/8/2025 Approved VINCENT HANLEY
ELECTRICAL-Rough 8/8/2025 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 8/8/2025 Approved VINCENT HANLEY
Green Building Rough 8/8/2025 Approved VINCENT HANLEY
HVAC-Rough 8/8/2025 Approved VINCENT HANLEY
Insulation 8/8/2025 Approved VINCENT HANLEY
ELECTRICAL-Rough 8/15/2025 Approved VINCENT HANLEY
Interior/Exterior Lathing 8/15/2025 Partial Approval VINCENT HANLEY
Drywall Nailing 8/29/2025 Approved MICHAEL CORTEZ
Special/Order Compliance 8/29/2025 Approved MICHAEL CORTEZ
Interior/Exterior Lathing 9/25/2025 Not Ready for Inspection DAVID MATSON
Shower Pan 9/25/2025 Corrections Issued DAVID MATSON
Interior/Exterior Lathing 9/29/2025 Approved VINCENT HANLEY
Shower Pan 9/29/2025 Approved VINCENT HANLEY
ELECTRICAL-Final 12/17/2025 Approved VINCENT HANLEY
Final 12/17/2025 OK to Issue CofO VINCENT HANLEY
Green Building Final 12/17/2025 Approved VINCENT HANLEY
HVAC-Final 12/17/2025 Approved VINCENT HANLEY
PLUMBING-Final 12/17/2025 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 12/17/2025 SGSOV Approved VINCENT HANLEY
Smoke Detectors 12/17/2025 Approved VINCENT HANLEY