680 E 45TH ST 90011
Certificate Information: 680 E 45TH ST 90011
- Application / Permit
- 24016-20000-17414
- Plan Check / Job No.
- B24VN07453
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN Exteior and interior remodel of existing SFD. New partitions, windows, doors, bathrooms remodeled, and kitchen.
- Permit Issued
- Issued on 7/12/2024
- Issuing Office
- Current Status
- Permit Finaled on 8/13/2025
Permit Application Status History
| Submitted | 5/31/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/5/2024 | SAMUEL GONZALEZ |
| Corrections Issued | 6/6/2024 | SAMUEL GONZALEZ |
| Applicant returned to address corrections | 6/21/2024 | SAMUEL GONZALEZ |
| No Progress | 7/10/2024 | SAMUEL GONZALEZ |
| Plan Check Approved | 7/12/2024 | SAMUEL GONZALEZ |
| Issued | 7/12/2024 | APPLICANT |
| Permit Finaled | 8/12/2025 | ALEJANDRO DE ARTOLA |
Permit Application Clearance Information
| Community Plan Implem. Overlay | Cleared | 7/8/2024 | ANACANY HURTADO |
Contact Information
| Contractor | L A Developing Inc; Lic. No.: 1083426-B | , |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 7/18/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 7/18/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 7/18/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Wood Frame | 7/18/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 7/22/2024 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 7/22/2024 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 7/22/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Wood Frame | 7/22/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 8/7/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Wood Frame | 8/7/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 8/9/2024 | Approved | ALEJANDRO DE ARTOLA |
| Wood Frame | 8/9/2024 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 8/15/2024 | Approved | ALEX COLIN |
| Drywall Nailing | 8/23/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 8/28/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 8/28/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 8/29/2024 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 8/29/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 6/4/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 6/4/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Gas Test | 6/4/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 6/4/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 6/4/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 6/4/2025 | SGSOV Not Ready | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 6/4/2025 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 6/12/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 6/12/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Gas Test | 6/12/2025 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 6/12/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 6/12/2025 | Approved | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 6/12/2025 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 6/16/2025 | Approved | ALEJANDRO DE ARTOLA |
| Final | 6/16/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 6/16/2025 | Approved | ALEJANDRO DE ARTOLA |
| Final | 7/10/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 7/15/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 7/16/2025 | Corrections Issued | RONNIE MEDINA |
| Final | 8/12/2025 | Permit Finaled | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 8/12/2025 | Approved | ALEJANDRO DE ARTOLA |