7027 N MATILIJA AVE 91405

Certificate Information: 7027 N MATILIJA AVE 91405

Application / Permit
24016-20000-17311
Plan Check / Job No.
B24VN07405
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) ATTACHED GARAGE TO (N) WORKSHOP ATTACHED TO (E) SFD, ALL WORK PER WFPP AND ENGINEER DETAIL." COMPLY WITH DEPARTMENT ORDER effectivc date 04/29/2024. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 8/14/2024
Issuing Office
Current Status
CofO Issued on 5/30/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/28/2024 APPLICANT
Assigned to Plan Check Engineer 5/31/2024 LUISANGEL VALENZUELA
Corrections Issued 6/1/2024 LUISANGEL VALENZUELA
Applicant returned to address corrections 7/8/2024 MADISON ODELL
Applicant returned to address corrections 8/2/2024 MADISON ODELL
Plan Check Approved 8/13/2024 MADISON O'DELL
Issued 8/14/2024 APPLICANT
CofO in Progress 4/25/2025 JOSE RUBIO
Permit Finaled 5/30/2025 DAVID JAMES
CofO Issued 5/30/2025 DAVID JAMES
Permit Finaled 5/30/2025 DAVID JAMES

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/7/2024 CARLOS AGUILERA
Sewer availability Cleared 6/7/2024 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Ding,, Wenzhuo; Lic. No.: C82891 5205 SUNNY POINT PL      RANCHO PALOS VERDES, CA 90275

Inspector Information

ARA SINANIAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
HASANTHA WEERASEKARA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
SCOTT SHUSTER, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOEL GUARDADO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARIYA MIHALEVA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOSE RUBIO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
DAVID JAMES, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
DAVID HICKMAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOHN HAMILTON, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOHN STEPHENS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
PIERRE VEGA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARK VAN SLOOTEN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MICKEY YAMASHITA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
RICHARD ROBLES, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
HAGOP BADOSSIAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
KIM BEAUCHAMP, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARK DOVICO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
THOMAS WOODS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
RAUL VASQUEZ, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
AUGUSTUS ALBAS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
LEO MILBAUER, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARIO CUEVAS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/27/2024 Partial Inspection JOSE RUBIO
Deputy Drilled-In Anchors 9/6/2024 Conditional Approval JOSE RUBIO
Footing/Foundation/Slab 9/9/2024 Approved JOSE RUBIO
Insulation 9/11/2024 Partial Inspection SCOTT SHUSTER
Pre-Inspection 9/11/2024 Partial Inspection SCOTT SHUSTER
Wood Frame 9/11/2024 Partial Inspection SCOTT SHUSTER
Deputy Wood Construction 10/18/2024 Conditional Approval JOSE RUBIO
Floor/Roof Diaphrgm/Shear Wall 10/18/2024 Partial Inspection JOSE RUBIO
BUILDING-Rough-Frame 10/21/2024 Not Ready for Inspection JOSE RUBIO
Drywall Nailing 10/21/2024 Not Ready for Inspection JOSE RUBIO
ELECTRICAL-Rough 10/21/2024 Not Ready for Inspection JOSE RUBIO
Floor/Roof Diaphrgm/Shear Wall 10/21/2024 Approved JOSE RUBIO
Green Building Rough 10/21/2024 Not Ready for Inspection JOSE RUBIO
Insulation 10/21/2024 Not Ready for Inspection JOSE RUBIO
Special/Order Compliance 10/21/2024 Not Ready for Inspection JOSE RUBIO
Wood Frame 10/21/2024 Not Ready for Inspection JOSE RUBIO
BUILDING-Rough-Frame 11/1/2024 Partial Inspection JOSE RUBIO
Drywall Nailing 11/1/2024 Not Ready for Inspection JOSE RUBIO
Green Building Rough 11/1/2024 Approved JOSE RUBIO
Insulation 11/1/2024 Approved JOSE RUBIO
Wood Frame 11/1/2024 Partial Inspection JOSE RUBIO
Drywall Nailing 12/12/2024 Partial Inspection JOSE RUBIO
BUILDING-Rough-Frame 2/7/2025 Approved JOSE RUBIO
Drywall Nailing 2/7/2025 Approved JOSE RUBIO
ELECTRICAL-Final 2/7/2025 Partial Inspection JOSE RUBIO
Final 2/7/2025 Partial Inspection JOSE RUBIO
Floor/Roof Diaphrgm/Shear Wall 2/7/2025 Approved JOSE RUBIO
Green Building Final 2/7/2025 Approved JOSE RUBIO
Insulation 2/7/2025 Approved JOSE RUBIO
SGSOV-Seismic Gas S/O Valve 2/7/2025 SGSOV Not Ready JOSE RUBIO
Smoke Detectors 2/7/2025 Partial Inspection JOSE RUBIO
Wood Frame 2/7/2025 Approved JOSE RUBIO
Interior/Exterior Lathing 2/20/2025 Approved JOSE RUBIO
ELECTRICAL-Final 4/22/2025 Partial Inspection JOSE RUBIO
Final 4/22/2025 Partial Inspection JOSE RUBIO
SGSOV-Seismic Gas S/O Valve 4/22/2025 SGSOV Approved JOSE RUBIO
Smoke Detectors 4/22/2025 Partial Inspection JOSE RUBIO
Final 4/24/2025 Partial Approval JOSE RUBIO
Smoke Detectors 4/24/2025 Approved JOSE RUBIO
Final 4/25/2025 OK to Issue CofO JOSE RUBIO