10447-10449 N MEMORY PARK AVE 91345
Certificate Information: 10447-10449 N MEMORY PARK AVE 91345
- Application / Permit
- 24016-20000-17202
- Plan Check / Job No.
- B24VN07355
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) ATTACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A).
- Permit Issued
- Issued on 6/17/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/10/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/24/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/3/2024 | ARTIN ZARUKIAN |
| Corrections Issued | 6/5/2024 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 6/10/2024 | APPLICANT |
| Plan Check Approved | 6/12/2024 | SERGIO MUNIZ |
| Issued | 6/17/2024 | APPLICANT |
| CofO in Progress | 6/6/2025 | JENNIFER RABUCHIN |
| Permit Finaled | 6/10/2025 | RUBEN SALAS |
| CofO Issued | 6/10/2025 | RUBEN SALAS |
| Permit Finaled | 6/10/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 6/11/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 6/11/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 6/11/2024 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Diamond Construction & Remodeling Inc; Lic. No.: 1041419-B | 11303 VISTA WAY CORONA, CA 92883 |
| Engineer | Vasquez,, Mario A; Lic. No.: C89006 | 1942 SPANISH BROOM DR PALMDALE, CA 93550 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/27/2024 | Conditional Approval | JOHN COLEMAN |
| Footing/Foundation/Slab | 6/27/2024 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 7/3/2024 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 7/3/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 7/3/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| PLUMBING-Rough | 7/3/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Sewer | 7/3/2024 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 7/17/2024 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Rough | 7/17/2024 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 7/17/2024 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 7/29/2024 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 7/29/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 7/29/2024 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 7/29/2024 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 8/20/2024 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 8/20/2024 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Rough | 8/20/2024 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 8/20/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Insulation | 8/20/2024 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 8/20/2024 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 8/26/2024 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 8/26/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Insulation | 8/26/2024 | Partial Approval | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 8/26/2024 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 9/3/2024 | Corrections Issued | JACK KARGODORIAN |
| HVAC-Rough | 9/3/2024 | Approved | JACK KARGODORIAN |
| Insulation | 9/3/2024 | Approved | JACK KARGODORIAN |
| Wood Frame | 9/11/2024 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 9/24/2024 | Approved | JENNIFER RABUCHIN |
| Pre-Inspection | 10/18/2024 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 11/15/2024 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 11/15/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 11/15/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 11/15/2024 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Final | 11/15/2024 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 11/15/2024 | SGSOV Not Ready | JENNIFER RABUCHIN |
| Smoke Detectors | 11/15/2024 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 11/25/2024 | SGSOV Not Required | MISAEL ESPARZA |
| Final | 12/5/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 12/5/2024 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 12/13/2024 | Approved | JENNIFER RABUCHIN |
| Final | 12/13/2024 | OK to Issue CofO | JENNIFER RABUCHIN |
| HVAC-Final | 12/13/2024 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 12/13/2024 | Approved | JENNIFER RABUCHIN |