13125-13127 W BEAVER ST 91342
Certificate Information: 13125-13127 W BEAVER ST 91342
- Application / Permit
- 24016-20000-17167
- Plan Check / Job No.
- B24VN07337
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (E) ATTACHED GARAGE CONVERT TO (N) ADU WITH PART OF (E) SFD PER CA Govt. Code65852.2(e)(1)(A)
- Permit Issued
- Issued on 7/10/2024
- Issuing Office
- Current Status
- CofO Issued on 3/25/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/24/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/31/2024 | SERGIO MUNIZ |
| Corrections Issued | 5/31/2024 | SERGIO MUNIZ |
| Plan Check Approved | 7/9/2024 | SERGIO MUNIZ |
| Issued | 7/10/2024 | APPLICANT |
| CofO in Progress | 2/14/2025 | KEVIN BERBERYAN |
| No Progress | 2/18/2025 | ROBERT GOLD |
| CofO in Progress | 2/18/2025 | ROBERT GOLD |
| CofO in Progress | 3/12/2025 | ROBERT GOLD |
| CofO in Progress | 3/19/2025 | ROBERT GOLD |
| Permit Finaled | 3/25/2025 | RUBEN SALAS |
| CofO Issued | 3/25/2025 | RUBEN SALAS |
| Permit Finaled | 3/25/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 6/4/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 6/4/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 6/4/2024 | BIAINA HARITUNIAN |
| Grading Pre-Inspection | Cleared | 7/8/2024 | CHARLES POWELL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Arutyunyan,, Vladimir; Lic. No.: C92714 | 331 ARDEN AVE SUIT 201 GLENDALE, CA 91203 |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/17/2024 | Partial Inspection | KEVIN BERBERYAN |
| Sewer | 7/26/2024 | Approved | KEVIN BERBERYAN |
| Underground Mechanical | 7/26/2024 | Approved | KEVIN BERBERYAN |
| Insulation | 7/30/2024 | Partial Approval | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 7/30/2024 | Partial Approval | KEVIN BERBERYAN |
| Deputy Drilled-In Anchors | 8/5/2024 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 8/7/2024 | Approved | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 9/10/2024 | Corrections Issued | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 9/10/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 10/1/2024 | Approved | KEVIN BERBERYAN |
| PLUMBING-Rough | 10/1/2024 | Approved | KEVIN BERBERYAN |
| Insulation | 10/21/2024 | Conditional Approval | KEVIN BERBERYAN |
| Drywall Nailing | 11/8/2024 | Approved | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 1/14/2025 | Approved | KEVIN BERBERYAN |
| Final | 1/14/2025 | Corrections Issued | KEVIN BERBERYAN |
| Green Building Final | 1/14/2025 | Approved | KEVIN BERBERYAN |
| Green Building Rough | 1/14/2025 | Approved | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 1/14/2025 | SGSOV Approved | KEVIN BERBERYAN |
| Smoke Detectors | 1/14/2025 | Approved | KEVIN BERBERYAN |
| Final | 1/21/2025 | OK to Issue CofO | KEVIN BERBERYAN |
| Final | 3/12/2025 | Corrections Issued | ROBERT GOLD |